The adopted FY2026-27 budget lists $580,000 for Road, Curbs, Gutter Rehab (210-450-45228), the same as the FY2025-26 approved budget [1] Budget line item detail.pdf, p. 23. A May 2024 staff report recommended using $3,087,033.68 from unallocated capital reserves for the Road and MUP Rehab 2024 Project after two bids came in, with Qualcon Contractors, Inc. the low base bidder at $2,707,194.25 [2] Agenda (PDF), p. 138[3] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2. Staff reports say the Town allocates $580,000 to Fund 210 each year and that unused funds carry over into the fund balance, which was $2,425,000 in May 2024 and $604,225.74 in May 2026 [2] Agenda (PDF), p. 138[4] Agenda (PDF), p. 252.

Updated

Findings

9 findings

  1. 1 The adopted FY2026-27 budget for Road, Curbs, Gutter Rehab is $580,000, the same as the FY2025-26 approved budget

    Updated

    The adopted FY2026-27 column of the Budget line item detail filed with the June 17, 2026 meeting lists $580,000 for account 210-450-45228, Road, Curbs, Gutter Rehab [1] Budget line item detail.pdf, p. 23. The same table lists an FY2025-26 approved budget of $580,000 and an FY2025-26 modified budget of $730,000 for the account [1] Budget line item detail.pdf, p. 23. By our calculation, the modified figure is $150,000 above the approved figure [1] Budget line item detail.pdf, p. 23.

    The FY26-27 Final Budget Adoption document, item 8, lists a "Continued allocation of $580,000 for Road rehabilitation and related capital projects supported by reserves" [2] Final Budget Adoption FY26-27.pdf, p. 6. The FY25-26 Final Budget lists the same item [3] FY25-26 Final Budget.pdf, p. 6.

    Earlier line-item tables show $580,000 as the approved FY2023-24 budget and the adopted FY2024-25 budget [4] Budget - Line Item Detail.pdf, p. 19. They show $580,000 as the approved FY2024-25 budget and the adopted FY2025-26 budget [5] Budget - Line Item Detail.pdf, p. 22.

    Why it matters

    The records show the same $580,000 figure for this account across several recent budgets, and the FY25-26 final budget describes it as roughly what the Town typically budgets each year for roads and infrastructure [6] FY25-26 Final Budget.pdf, p. 30[1] Budget line item detail.pdf, p. 23.

    Sources

    1. Budget line item detail.pdf

      attachmentmeeting/filed datep. 23

    2. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 6

    3. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 6

    4. Budget - Line Item Detail.pdf

      attachmentmeeting/filed datep. 19

    5. Budget - Line Item Detail.pdf

      attachmentmeeting/filed datep. 22

    6. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 30

  2. 2 Staff recommended $3,087,033.68 from unallocated capital reserves for the Road and MUP Rehab 2024 Project

    Updated

    A staff report in the agenda packet for the May 15, 2024 meeting says staff recommended using funds from unallocated capital reserves to cover the base bid and Alternate 1 plus 10% contingency, for a total of $3,087,033.68 [1] Agenda (PDF), p. 138. The attachment titled "Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc." carries the same text [2] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2.

    The report lists the funding sources as: Road Rehab fund balance $1,617,537.85; remaining FY23/24 Fund 210 $500,000.00; FY24/25 Fund 210 $400,000.00; Fund Balance – Future Capital 990 $460,375.83; and MCWD Reimbursement $109,120.00 [1] Agenda (PDF), p. 138.

    The pages provided do not show the Council's vote [1] Agenda (PDF), p. 138.

    Why it matters

    The proposed funding for this project came from several sources, including the Fund 210 balance and capital reserves, and was not limited to one year's $580,000 allocation [1] Agenda (PDF), p. 138.

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 138

    2. Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf

      attachmentmeeting/filed datep. 2

  3. 3 Two bids were received for the Road and MUP Rehab 2024 Project; Qualcon Contractors, Inc. was low at $2,707,194.25

    Updated

    The staff report says staff solicited bids beginning April 8, 2024, and the bids were publicly opened on May 3, 2024, at 3:00 PM [1] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2. Two bids were received with base bid pricing of $2,707,194.25 from Qualcon Contractors, Inc. and $3,073,145.65 from Spiess Construction Co, Inc. [1] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2. The report says a bid review found no irregularities [1] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2.

    The report says the low base bid was below the engineer's estimate of $3,200,000 [2] Agenda (PDF), p. 138. It says Alternate 1 (raising Mammoth Community Water District utility covers) was included at MCWD's request, that MCWD will reimburse the Town, and that the MCWD work is worth approximately $109,120 [2] Agenda (PDF), p. 138.

    Why it matters

    The low base bid was lower than the engineer's estimate and lower than the other bid received [2] Agenda (PDF), p. 138[1] Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf, p. 2.

    Sources

    1. Award contract for the Road and MUP Rehab 2024 Project to Qualcon Contractors Inc.pdf

      attachmentmeeting/filed datep. 2

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 138

  4. 4 Staff reports put the Fund 210 road fund balance at $2,425,000 in May 2024 and $604,225.74 in May 2026

    Updated

    The May 2024 staff report says unused funds are carried over into the fund balance, which "has been increasing over the past few years and is currently $2,425,000" [1] Agenda (PDF), p. 138. It says staff proposed using $807,462.15 of that balance for a separate slurry seal contract and $1,617,537.85 for the 2024 road project [1] Agenda (PDF), p. 138. By our calculation, those two amounts equal $2,425,000 [1] Agenda (PDF), p. 138.

    The staff narrative in the May 6, 2026 agenda packet on the 2026 Slurry Seal Project says the Town budgets $580,000 to FD 210 each fiscal year and that the fund balance is currently $604,225.74 [2] Agenda (PDF), p. 252. The FY25-26 Final Budget says the Town typically budgets approximately $580,000 each year for roads and infrastructure, and that this is sometimes carried over to a future year for a larger project [3] FY25-26 Final Budget.pdf, p. 30.

    Why it matters

    The pages provided do not explain the change between $2,425,000 and $604,225.74 [1] Agenda (PDF), p. 138[2] Agenda (PDF), p. 252.

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 138

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 252

    3. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 30

  5. 5 Staff recommended allocating $439,630.29 from Fund 210 for the 2026 Slurry Seal Project, leaving $164,595.45

    Updated

    The staff report in the agenda packet for the May 6, 2026 meeting says the low bid for the 2026 Slurry Seal Project was $399,663.90, below the engineer's estimate of $700,000 [1] Agenda (PDF), p. 252. It says staff recommend allocating funds to cover the bid plus 10% contingency, a total of $439,630.29 from FD 210 [1] Agenda (PDF), p. 252. It says the remaining Road Rehab fund balance of $164,595.45 will be available for other projects [1] Agenda (PDF), p. 252.

    Why it matters

    If the recommended allocation goes ahead as described, most of the Fund 210 balance reported in May 2026 would be committed to this project [1] Agenda (PDF), p. 252.

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 252

  6. 6 Recorded spending in the account has varied widely from year to year

    Updated

    Budget documents list actual spending for account 210-450-45228 of $1,350,943 in FY2017-18 [1] 2019-20 Budget, p. 78 and $18,507.70 in FY2018-19 [2] 2019-2020 Budget Book, p. 121. They list $69,595 in FY2019-20 and $99,007 in FY2020-21 [3] 2022-2023 Budget Book, p. 125.

    The FY2019-20 adopted budget for the account was $580,000 [2] 2019-2020 Budget Book, p. 121. The FY2020-21 Council Adopted Budget says that in the most recent year, STIP funds were used for Lower Main Street and no Road Rehab project was pursued [4] 2020-2021 Council Adopted Budget, p. 30.

    Why it matters

    The records show spending in the account far above and far below the $580,000 annual budget in different years [2] 2019-2020 Budget Book, p. 121[1] 2019-20 Budget, p. 78[5] Budget - Line Item Detail.pdf, p. 19.

    Sources

    1. 2019-20 Budget

      financialfiscal year from document title Document date (fiscal year from document title) p. 78

    2. 2019-2020 Budget Book

      financialfiscal year from document title Document date (fiscal year from document title) p. 121

    3. 2022-2023 Budget Book

      financialfiscal year from document title Document date (fiscal year from document title) p. 125

    4. 2020-2021 Council Adopted Budget

      financialfiscal year from document title Document date (fiscal year from document title) p. 30

    5. Budget - Line Item Detail.pdf

      attachmentmeeting/filed datep. 19

  7. 7 Town documents give two different FY2022-23 budget figures for the account: $580,000 and $430,000

    Updated

    The Final Budget Line Item Detail filed with the June 15, 2022 meeting lists a Council approved budget for FY22-23 of $580,000, with approved and modified FY21-22 budgets of $580,000 [1] Final Budget Line Item Detail.pdf, p. 19. The FY2022/23 Adopted Budget book lists $430,000 as the 2022-23 adopted budget [2] 2022-2023 Budget Book, p. 125. The Budget Line Item Detail filed with the June 21, 2023 meeting lists $430,000 as the approved and modified FY22-23 budget and $580,000 as the adopted FY23-24 budget [3] Budget - Line Item Detail.pdf, p. 19.

    Why it matters

    The FY2022-23 figure for this account differs between a June 2022 line-item table and the adopted budget book [1] Final Budget Line Item Detail.pdf, p. 19[2] 2022-2023 Budget Book, p. 125. The pages provided do not explain the difference [1] Final Budget Line Item Detail.pdf, p. 19[2] 2022-2023 Budget Book, p. 125.

    Sources

    1. Final Budget Line Item Detail.pdf

      attachmentmeeting/filed datep. 19

    2. 2022-2023 Budget Book

      financialfiscal year from document title Document date (fiscal year from document title) p. 125

    3. Budget - Line Item Detail.pdf

      attachmentmeeting/filed datep. 19

  8. 8 Road Rehabilitation (210-450-45228) covered part of the cost of the Lake Mary Road Sidewalk

    Updated

    The 2020-2021 Council Adopted Budget says the Lake Mary Road Sidewalk was awarded by Town Council on April 15 in the amount of $168,132, not including staff time or contingency [1] 2020-2021 Council Adopted Budget, p. 30. It says the project is funded with a $29,204 contribution from the property owner and $94,000 in RSTP funding, "with the difference being made up by Road Rehabilitation (210-450-45228)" [1] 2020-2021 Council Adopted Budget, p. 30. By our calculation, that difference is $44,928 [1] 2020-2021 Council Adopted Budget, p. 30.

    The document adds: "Alternatively, the Town's contribution was approved by Town Council for SB1 funding" [1] 2020-2021 Council Adopted Budget, p. 30.

    Why it matters

    The Town document shows this account being used to fill part of a funding gap on a sidewalk project, with a possible alternative SB1 source [1] 2020-2021 Council Adopted Budget, p. 30.

    Sources

    1. 2020-2021 Council Adopted Budget

      financialfiscal year from document title Document date (fiscal year from document title) p. 30

  9. 9 The FY25-26 Final Budget lists a $3,000,000 total budget for the 2025 Road and MUP Rehabilitation Project (ST1)

    Updated

    The FY25-26 Final Budget filed with the June 18, 2025 meeting lists "Total Budget FY25-26: $3,000,000" for the 2025 Road and MUP Rehabilitation Project (ST1) [1] FY25-26 Final Budget.pdf, p. 34. The FY25-26 Final Budget includes pulverizing existing AC pavement, recompacting base and placing new hot mix asphalt [1] FY25-26 Final Budget.pdf, p. 34.

    Concrete swale work is described at intersections of Forest Trail with Grindelwald Rd, Holiday Way, Rainbow Lane and Convict Dr; Ridge Way with Minaret Rd and Panorama Dr; Majestic Pines Dr and Valley Vista Dr; and Old Mammoth Rd and Meridian Blvd [1] FY25-26 Final Budget.pdf, p. 34. The FY25-26 Final Budget also covers the path along Sawmill Cutoff Rd and work within Shady Rest Park [1] FY25-26 Final Budget.pdf, p. 34.

    The page does not say which account or fund pays for this project [1] FY25-26 Final Budget.pdf, p. 34.

    Why it matters

    The page provided does not link it to account 210-450-45228 [1] FY25-26 Final Budget.pdf, p. 34.

    Sources

    1. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34