  <title>2026 Asphalt and Concrete Maintenance Project (CIP ST18) · Transparent Mammoth</title>
  <id>tag:transparentmammoth.com,2026:topics/cip-st18</id>
  <updated>2026-10-18T00:00:00Z</updated>
  <author><name>Transparent Mammoth</name></author>
  <link rel="self" type="application/atom+xml" href="https://beta.transparentmammoth.com/topics/cip-st18/feed.xml"/>
  <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/"/>
<subtitle>The Town&#39;s FY2026-27 budget documents list a total budget of $150,000 for the 2026 Asphalt and Concrete Maintenance Project (CIP ST18)  (Tentative Budget FY26-27.pdf, p. 17.1) (Final Budget Adoption FY26-27.pdf, p. 36.1). The figure appears in the Tentative Budget filed with the June 3, 2026 meeting and in the Final Budget Adoption FY26-27 filed with the June 17, 2026 meeting  (Tentative Budget FY26-27.pdf, p. 17.1) (Final Budget Adoption FY26-27.pdf, p. 36.1). Both documents say the Town set aside funds for winter 25-26 damage but had not yet developed the scope of work, because winter damage assessments were incomplete  (Tentative Budget FY26-27.pdf, p. 17.1) (Final Budget Adoption FY26-27.pdf, p. 36.1). A carry-over table filed with the September 2, 2026 meeting lists $150,000 for ST18, in the phase labeled CON, all under the TOML - GF Committed column  (Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1) (Agenda (PDF), p. 52).</subtitle>  <entry>
    <title>Town budget documents list a $150,000 FY2026-27 total budget for the 2026 Asphalt and Concrete Maintenance Project</title>
    <id>tag:transparentmammoth.com,2026:topics/cip-st18/finding/1</id>
    <updated>2026-10-18T00:00:00Z</updated>
    <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/#finding-1"/>
    <category term="machine" scheme="provenance"/>
    <content type="text">The Final Budget Adoption FY26-27, filed with the June 17, 2026 meeting, lists &#34;Total Budget FY26-27: $150,000&#34; for the 2026 Asphalt and Concrete Maintenance Project  (Final Budget Adoption FY26-27.pdf, p. 36.1) (Final Budget Adoption FY26-27.pdf, p. 45). The June 17, 2026 agenda packet reproduces the same entry at page 182 of 394  (Agenda (PDF), p. 182).

The same $150,000 figure appears earlier  (Tentative Budget FY26-27.pdf, p. 17.1) (Agenda (PDF), p. 115). The Tentative Budget FY26-27 (filed with the June 3, 2026 meeting) and the June 3, 2026 agenda packet each list &#34;Total Budget FY26-27: $150,000&#34;  (Tentative Budget FY26-27.pdf, p. 17.1) (Agenda (PDF), p. 115).

A Draft 26-27 Master Project List filed with the March 11, 2026 meeting shows a different figure  (Draft 26-27 Master Project List.pdf, p. 1). Its ST18 row has $125,000 in what appears to be the 26/27 column, and its Total cell reads &#34;$125,000 $150,000&#34;  (Draft 26-27 Master Project List.pdf, p. 1).
Why it matters: These are budget figures, not spending  (Final Budget Adoption FY26-27.pdf, p. 36.1) (Tentative Budget FY26-27.pdf, p. 17.1). The March draft list shows a $125,000 entry, while the June tentative and final budget documents show $150,000  (Draft 26-27 Master Project List.pdf, p. 1) (Tentative Budget FY26-27.pdf, p. 17.1) (Final Budget Adoption FY26-27.pdf, p. 36.1).</content>
  </entry>
  <entry>
    <title>The budget text says the project&#39;s scope of work had not been developed because winter damage assessments were incomplete</title>
    <id>tag:transparentmammoth.com,2026:topics/cip-st18/finding/2</id>
    <updated>2026-10-18T00:00:00Z</updated>
    <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/#finding-2"/>
    <category term="machine" scheme="provenance"/>
    <content type="text">The Final Budget Adoption FY26-27 says damage is done each winter to roads, multi-use paths, sidewalks, drainage infrastructure and other Town-owned elements in the public right-of-way  (Final Budget Adoption FY26-27.pdf, p. 36.1). It says the Town &#34;set aside funds during the 2nd quarter to address any issues that arose from the winter of 25-26&#34;  (Final Budget Adoption FY26-27.pdf, p. 36.1). The same text says &#34;the scope of work has not yet been developed for this effort as winter damage assessments have not yet been completed&#34;  (Final Budget Adoption FY26-27.pdf, p. 36.1).

The Tentative Budget FY26-27 (filed with the June 3, 2026 meeting) and the June 3, 2026 agenda packet contain the same statements  (Tentative Budget FY26-27.pdf, p. 17.1) (Agenda (PDF), p. 115). The June 17, 2026 agenda packet repeats them  (Agenda (PDF), p. 182).
Why it matters: As of the June 3 and June 17, 2026 documents, the Town had allocated $150,000 but had not defined what work it would cover  (Agenda (PDF), p. 115) (Agenda (PDF), p. 182).</content>
  </entry>
  <entry>
    <title>The funds are described as supplementing the road rehabilitation budget</title>
    <id>tag:transparentmammoth.com,2026:topics/cip-st18/finding/3</id>
    <updated>2026-10-18T00:00:00Z</updated>
    <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/#finding-3"/>
    <category term="machine" scheme="provenance"/>
    <content type="text">The Final Budget Adoption FY26-27 says &#34;these funds will supplement the road rehabilitation budget to make repairs to infrastructure as needed&#34;  (Final Budget Adoption FY26-27.pdf, p. 36.1). The Tentative Budget FY26-27 and the June 17, 2026 agenda packet use the same wording  (Tentative Budget FY26-27.pdf, p. 17.1) (Agenda (PDF), p. 182).

In the same Final Budget Adoption document, the separate 2026 Slurry Seal Project is described as &#34;funded by road rehabilitation dollars&#34; with a Total Budget FY26-27 of $700,000  (Final Budget Adoption FY26-27.pdf, p. 36.1).
Why it matters: The records describe the $150,000 as an addition to existing road rehabilitation money, to be used for repairs &#34;as needed&#34;  (Final Budget Adoption FY26-27.pdf, p. 36.1).</content>
  </entry>
  <entry>
    <title>A September 2, 2026 carry-over table lists $150,000 for ST18 under TOML - GF Committed, in the phase labeled CON</title>
    <id>tag:transparentmammoth.com,2026:topics/cip-st18/finding/4</id>
    <updated>2026-10-18T00:00:00Z</updated>
    <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/#finding-4"/>
    <category term="machine" scheme="provenance"/>
    <content type="text">The September 2, 2026 agenda packet (page 52 of 72) shows the same row  (Agenda (PDF), p. 52).

The drafts&#39; reading of it as &#34;Construction&#34; is therefore not confirmed here  (Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1).

The extracted table text is garbled, so the year columns cannot be confirmed  (Table 4 - 26-27 5-year CIP.pdf, p. 1).
Why it matters: The table labels the phase &#34;CON&#34;  (Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1).</content>
  </entry>
  <entry>
    <title>ST18 appears on the Town&#39;s draft 2026/27 five-year CIP project lists</title>
    <id>tag:transparentmammoth.com,2026:topics/cip-st18/finding/5</id>
    <updated>2026-10-18T00:00:00Z</updated>
    <link rel="alternate" type="text/html" href="https://beta.transparentmammoth.com/topics/cip-st18/#finding-5"/>
    <category term="machine" scheme="provenance"/>
    <content type="text">The DRAFT 2026-27 CIP Project List (Table 4, filed with the March 3, 2026 meeting) includes the 2026 Asphalt and Concrete Maintenance Project  (DRAFT 2026-27 CIP Project List.pdf, p. 1). ST18 appears there in a cell listing ST3, ST4, ST6, ST10, ST12, ST16, ST17, ST18 and ST19 under a &#34;Streets&#34; label  (DRAFT 2026-27 CIP Project List.pdf, p. 1).

The Draft 26-27 Master Project List filed with the March 11, 2026 meeting lists ST18 in its &#34;Streets&#34; section  (Draft 26-27 Master Project List.pdf, p. 1).
Why it matters: The project was on the Town&#39;s draft five-year capital list in March 2026, before the June budget documents that carry the $150,000 total budget  (DRAFT 2026-27 CIP Project List.pdf, p. 1) (Draft 26-27 Master Project List.pdf, p. 1) (Tentative Budget FY26-27.pdf, p. 17.1).</content>