2026 Slurry Seal Project (CIP ST16)

The May 6, 2026 Town Council minutes show the consent agenda carried 5 to 0, with Mayor Rice recused on item 9.5, the award of the 2026 Slurry Seal Project contract to Pavement Coatings Co. [1] Minutes (PDF), p. 4. In the staff report, Pavement Coatings Co. was the low bidder of eight at $399,663.90, and the engineer's estimate was $700,000 [2] Agenda (PDF), p. 250[3] Award contract for 2026 Slurry Seal project.pdf, p. 2[4] Award contract for 2026 Slurry Seal project.pdf, p. 3. The FY26-27 budget documents list a Total Budget FY26-27 of $700,000 for the project, funded by road rehabilitation dollars [5] Final Budget Adoption FY26-27.pdf, p. 36.1. At the September 2, 2026 Town Council meeting, a speaker said material shortages had pushed the work to September 29 [6] Town Council — 2026-09-02 16:00:00, 1:57:46.

Updated

Findings

9 findings

  1. 1 Council carried the consent agenda, including the 2026 Slurry Seal contract award to Pavement Coatings Co., on May 6, 2026

    Updated

    The May 6, 2026 Town Council minutes record a motion to approve the consent agenda with Mayor Rice recused on items 9.3 and 9.5 [1] Minutes (PDF), p. 4. The motion carried 5 to 0 [1] Minutes (PDF), p. 4. Item 9.5 on that consent agenda was "Award contract for the 2026 Slurry Seal Project to Pavement Coatings Co." [1] Minutes (PDF), p. 4[2] Agenda (HTML), p. 1.

    Award contract for the 2026 Slurry Seal Project to Pavement Coatings Company." [3] Town Council — 2026-05-06 16:00:00, 2:02:08

    Staff recommended that Council approve the plans and specifications and award the Base Bid to the lowest responsive bidder, Pavement Coatings Co., in the amount of $399,663.90, according to the staff report for the item [4] Agenda (PDF), p. 250. Staff also recommended authorizing the Town Manager to execute the construction contract [4] Agenda (PDF), p. 250. The minutes page cited here does not itself restate these recommendations as terms of the motion [1] Minutes (PDF), p. 4.

    Why it matters

    The Mayor's recusal on this item is also recorded [1] Minutes (PDF), p. 4.

    Sources

    1. Minutes (PDF)

      minutes_pdfmeeting/filed datep. 4

    2. Agenda (HTML)

      agenda_htmlmeeting/filed datep. 1

    3. Town Council — 2026-05-06 16:00:00

      transcriptmeeting/filed date

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 250

  2. 2 Pavement Coatings Co. was the lowest of eight bids, at $399,663.90

    Updated

    Bids were publicly opened on April 24, 2026, at 4:00 PM, and eight bids were received [1] Award contract for 2026 Slurry Seal project.pdf, p. 2. The base bids were: Pavement Coatings Co. $399,663.90; American Asphalt South, Inc. $448,505.38; Sierra Nevada Construction, Inc. $452,007.00; VSS International Inc. $493,325.00; Doolittle Construction LLC $515,000.00; Dryco Construction, Inc. $537,537.00; American Pavement Systems, Inc. $547,671.81; and Roy Allan Slurry Seal, Inc. $709,291.27 [1] Award contract for 2026 Slurry Seal project.pdf, p. 2. The report says a bid review found no irregularities [2] Award contract for 2026 Slurry Seal project.pdf, p. 3. It also says the low bid was below the engineer's estimate of $700,000 [2] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    The first page lists Canyon Boulevard, Canyon Place, Lakeview Boulevard, Lakeview Road, Rainbow Lane, Rainbow Place, Forest Trail (from Lakeview to Minaret) and Forest Lane [3] Agenda (PDF), p. 250. The next page continues the list with Forest Place, Hillside Drive, Hillside Place, Hillside Court, Crest Lane, Ridgecrest Drive, Ridgecrest Place, Mammoth Slopes Drive, Top of Slopes Court, Aspen Lane, Aspen Place, Convict Drive, Convict Place, Twin Lakes Lane, Jahan Drive, Snowridge Lane, Beaver Trail, Beaver Place, Beaver Court, Larkspur Lane, Crystal Lane and Horseshoe Drive [1] Award contract for 2026 Slurry Seal project.pdf, p. 2. It adds that additional roads may be added later if additional funding is allocated [1] Award contract for 2026 Slurry Seal project.pdf, p. 2.

    Why it matters

    The staff report also lists which streets the recommended contract covers [1] Award contract for 2026 Slurry Seal project.pdf, p. 2[2] Award contract for 2026 Slurry Seal project.pdf, p. 3[3] Agenda (PDF), p. 250.

    Sources

    1. Award contract for 2026 Slurry Seal project.pdf

      attachmentmeeting/filed datep. 2

    2. Award contract for 2026 Slurry Seal project.pdf

      attachmentmeeting/filed datep. 3

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 250

  3. 3 Staff recommended allocating $439,630.29 from Fund 210 for the slurry seal bid plus a 10% contingency

    Updated

    The May 6, 2026 staff report says the Town budgets $580,000 each fiscal year to FD 210 for road maintenance [1] Award contract for 2026 Slurry Seal project.pdf, p. 3. That covers work such as annual crack sealing, pothole repair, striping and pavement markings, and other rehabilitation projects [1] Award contract for 2026 Slurry Seal project.pdf, p. 3. The report says unused funds carry over into the fund balance, and that the balance was then $604,225.74 [1] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    The report says staff recommended allocating funds to cover the bid plus 10% contingency, for a total of $439,630.29 from FD 210 [1] Award contract for 2026 Slurry Seal project.pdf, p. 3. It says the remaining Road Rehab fund balance of $164,595.45 would be available for other projects [1] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Why it matters

    The staff report states how much of that fund balance would remain for other projects if the recommended allocation were made [1] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Sources

    1. Award contract for 2026 Slurry Seal project.pdf

      attachmentmeeting/filed datep. 3

  4. 4 FY26-27 budget documents list a Total Budget FY26-27 of $700,000 for the project, funded by road rehabilitation dollars

    Updated

    The Final Budget Adoption FY26-27 document, filed with the June 17, 2026 meeting, lists the 2026 Slurry Seal Project with "Total Budget FY26-27: $700,000" [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It says the project "is funded by road rehabilitation dollars" and that work "is expected to be completed over the summer" [1] Final Budget Adoption FY26-27.pdf, p. 36.1. The Tentative Budget FY26-27 (filed with the June 3, 2026 meeting) and the June 3 and June 17, 2026 agenda packets contain the same $700,000 figure and the same description [2] Tentative Budget FY26-27.pdf, p. 17.1[3] Agenda (PDF), p. 114[4] Agenda (PDF), p. 181.

    The May 6, 2026 staff report put the engineer's estimate at $700,000 and the low bid at $399,663.90 [5] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Why it matters

    The $700,000 is a budget figure for FY26-27 [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It is not a contract amount or spending [1] Final Budget Adoption FY26-27.pdf, p. 36.1. The contract-award staff report, written earlier, lists a lower low-bid figure [5] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Sources

    1. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 36.1

    2. Tentative Budget FY26-27.pdf

      attachmentmeeting/filed datep. 17.1

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 114

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 181

    5. Award contract for 2026 Slurry Seal project.pdf

      attachmentmeeting/filed datep. 3

  5. 5 CIP tables show $500,000 in a March 2026 draft and a $400,000 General Fund-committed carry-over in September 2026

    Updated

    The "CIP Budget Outlook for 25/26 Carry Over to 26/27" table was filed with the September 2, 2026 agenda [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[2] Agenda (PDF), p. 52. It lists ST16, 2026 Slurry Seal Project, in the construction (CON) phase with Totals of $400,000, all under the "TOML - GF Committed" column [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[2] Agenda (PDF), p. 52.

    Why it matters

    They show $500,000, $400,000 and, in the budget documents, $700,000 for the same project [3] Agenda (PDF), p. 20[1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[4] Final Budget Adoption FY26-27.pdf, p. 36.1. The September table names General Fund-committed money, while the budget text says road rehabilitation dollars [3] Agenda (PDF), p. 20[1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[4] Final Budget Adoption FY26-27.pdf, p. 36.1.

    Sources

    1. Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf

      attachmentmeeting/filed datep. 1

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 52

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 20

    4. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 36.1

  6. 6 At the September 2, 2026 meeting, a speaker said slurry seal work slipped to September 29 because material was unavailable

    Updated

    At the September 2, 2026 Town Council meeting, a speaker giving a project update said at 2:02:03 in the recording that a week earlier they would have said the work would occur "last Monday because that's what we were being told [1] Town Council — 2026-09-02 16:00:00, 1:57:46. The next day we were told material is not available" [1] Town Council — 2026-09-02 16:00:00, 1:57:46. The next day, they told us the material would not be available, and now it's happening on September 29th" [1] Town Council — 2026-09-02 16:00:00, 1:57:46. The speaker added that an email said "they're switching to a new provider, and stand by, we may be able to get it done sooner" [1] Town Council — 2026-09-02 16:00:00, 1:57:46.

    They said until it is available "they cannot make the slurry and we cannot complete the project" [1] Town Council — 2026-09-02 16:00:00, 1:57:46. At 2:03:00 the speaker said, "If it goes too late, I will delay it because we're not going to put slurry down in the middle of winter" [1] Town Council — 2026-09-02 16:00:00, 1:57:46.

    A responding speaker said that if the date could not be fixed and the work got pushed, the Town would have the contractor come back and re-stripe [1] Town Council — 2026-09-02 16:00:00, 1:57:46.

    Why it matters

    Earlier FY26-27 budget documents said work was expected to be completed over the summer [2] Final Budget Adoption FY26-27.pdf, p. 36.1. The September 2 recording shows the work had not been done by then and was reported as set for September 29 [1] Town Council — 2026-09-02 16:00:00, 1:57:46.

    Sources

    1. Town Council — 2026-09-02 16:00:00

      transcriptmeeting/filed date

    2. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 36.1

  7. 7 The Town describes a 5-year plan to treat all roads, with the Slopes neighborhood bid for 2026

    Updated

    The Final Budget Adoption FY26-27 says the Town started an annual slurry and fog seal program in 2024 [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It says treatments were tested and evaluated that first year, and that the Town then "developed a plan to treat all of the roads in Town once every 5 years" [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It says that in 2025 the Town bid and awarded a slurry project to treat roads in the Knolls neighborhood, the first section of Town to be treated [1] Final Budget Adoption FY26-27.pdf, p. 36.1. For 2026 it says the Town "has bid the slopes neighborhood" [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It also says that in advance of the work the Town road department crack sealed and patched all of the roads within the extent of the work [1] Final Budget Adoption FY26-27.pdf, p. 36.1[2] Agenda (PDF), p. 181.

    Why it matters

    The document filed with the June 17, 2026 meeting describes the 2026 project as one phase of a multi-year plan, covering the Slopes neighborhood after the Knolls neighborhood in 2025 [1] Final Budget Adoption FY26-27.pdf, p. 36.1.

    Sources

    1. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 36.1

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 181

  8. 8 The 2026 Slurry Seal Project is described as exempt from CEQA under Section 15301(c)

    Updated

    The May 6, 2026 staff report says the project involves operation, repair, maintenance or minor alteration of existing highways and streets and similar facilities [1] Award contract for 2026 Slurry Seal project.pdf, p. 3. It also says the National Environmental Policy Act (NEPA) was not required for this project [1] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Why it matters

    This is the environmental basis the staff report states for proceeding without further CEQA review [1] Award contract for 2026 Slurry Seal project.pdf, p. 3.

    Sources

    1. Award contract for 2026 Slurry Seal project.pdf

      attachmentmeeting/filed datep. 3

  9. 9 Earlier history: the 2024 Street Slurry Seal Project (ST16) carried different budget figures in different FY2024-25 documents

    Updated

    The Final Budget Adoption FY24-25, filed with the June 19, 2024 meeting, says the 2024 Street Slurry Seal Project (ST16) "will be awarded in spring 2024" and that work was expected over the summer/fall of 2024 [1] Final Budget Adoption FY24-25.pdf, p. 45.1. It lists Total Budget FY24-25 of $900,000 and a scope of Minaret Road, Chateau Road, Old Mammoth Road, Meridian Blvd, Azimuth Drive, Canyon Boulevard and Forest Trail [1] Final Budget Adoption FY24-25.pdf, p. 45.1. The 2024-2025 Budget Book gives the same scope and timing language but lists Total Budget FY24-25 of $715,000 [2] 2024-2025 Budget Book, p. 163.1. The "CIP Budget Outlook for 23/24 Carry Over to 24/25" table, filed with the August 7, 2024 meeting, lists ST16 2024 Street Slurry Seal Project at $735,000 in the construction phase [3] Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf, p. 1.

    Why it matters

    The same project number, ST16, was used for a 2024 slurry seal project with its own budget figures [1] Final Budget Adoption FY24-25.pdf, p. 45.1[2] 2024-2025 Budget Book, p. 163.1[3] Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf, p. 1. Readers comparing project costs across years should note the different figures and labels [1] Final Budget Adoption FY24-25.pdf, p. 45.1[2] 2024-2025 Budget Book, p. 163.1[3] Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf, p. 1.

    Sources

    1. Final Budget Adoption FY24-25.pdf

      attachmentmeeting/filed datep. 45.1

    2. 2024-2025 Budget Book

      financialfiscal year from document title Document date (fiscal year from document title) p. 163.1

    3. Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf

      attachmentmeeting/filed datep. 1