2026 Townwide Striping Project (CIP ST17)
The Town's FY2026-27 budget document describes a plan to hire an outside contractor to restripe Town roads from a new plan set, replacing annual repainting by Public Works staff [1] Final Budget Adoption FY26-27.pdf, p. 36.1[2] Final Budget Adoption FY26-27.pdf, p. 45. A September 2, 2026 carry-over table lists $215,000 for the project from FY2025-26 into FY2026-27, in the "CON" phase and in the "TOML - GF Committed" column [3] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. The project's amount differs between CIP tables ($125,000 in March and July 2026 tables, $215,000 in the September table), and the budget text's "late spring 2026" completion date sits beside a carry-over listed in September [4] Agenda (PDF), p. 5[5] Agenda (PDF), p. 27[6] Agenda (PDF), p. 55[1] Final Budget Adoption FY26-27.pdf, p. 36.1.
Updated
Findings
6 findings
-
1 The Town plans to hire a contractor to restripe roads from a new plan set instead of repainting with Public Works staff
Updated
The FY26-27 budget text says the Town of Mammoth Lakes traditionally performs annual maintenance on the linear striping of roads because of excessive wear from snow removal operations during the winter season [1] Final Budget Adoption FY26-27.pdf, p. 45. It says Public Works staff typically re-paint all linear striping each year in the spring, which takes labor hours and specialized equipment and takes time away from the crew's other duties [1] Final Budget Adoption FY26-27.pdf, p. 45.
The Final Budget Adoption FY26-27 says this has created the appearance of multiple layers of striping that can cause confusion about where the lanes are supposed to be [1] Final Budget Adoption FY26-27.pdf, p. 45.
By developing a plan set and contracting externally, the text says, the Town can coordinate to have all of its linear striping completed annually in a timely manner once spring weather permits, while freeing up Public Works staff for other maintenance [1] Final Budget Adoption FY26-27.pdf, p. 45. The proposed work also involves removing old linear striping where it conflicts with the official plan set or layout [1] Final Budget Adoption FY26-27.pdf, p. 45. The same text appears in the June 17, 2026 agenda packet [2] Agenda (PDF), p. 182 and in the Final Budget Adoption FY26-27 document [3] Final Budget Adoption FY26-27.pdf, p. 36.1.
Why it matters
The Final Budget Adoption FY26-27 states the reason as lane confusion from overlapping striping and the staff time the work takes [1] Final Budget Adoption FY26-27.pdf, p. 45.
Sources
- Final Budget Adoption FY26-27.pdf
- Agenda (PDF)
- Final Budget Adoption FY26-27.pdf
-
2 The FY2026-27 budget document lists a Total Budget FY26-27 of $200,000 for the striping project
Updated
The Final Budget Adoption FY26-27 document, filed with the June 17, 2026 meeting, lists "Total Budget FY26-27: $200,000" under the 2026 Townwide Striping Project [1] Final Budget Adoption FY26-27.pdf, p. 36.1. The same entry appears on page 182 of the June 17, 2026 agenda packet, which is marked "Fiscal Year 26-27 Final Budget Page 45" [2] Agenda (PDF), p. 182. It also appears on page 45 of the Final Budget Adoption document [3] Final Budget Adoption FY26-27.pdf, p. 45.
Why it matters
This is the project amount shown in the FY2026-27 final document filed with the June 17, 2026 meeting filed with the June 17, 2026 meeting [1] Final Budget Adoption FY26-27.pdf, p. 36.1.
Sources
- Final Budget Adoption FY26-27.pdf
- Agenda (PDF)
- Final Budget Adoption FY26-27.pdf
-
3 A September 2, 2026 table lists $215,000 carried over from FY2025-26 for the striping project, in the CON phase
Updated
Table 1, "CIP Budget Outlook for 25/26 Carry Over to 26/27," lists ST17, 2026 Townwide Striping Project, with phase "CON" and a total of $215,000 [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. The same $215,000 appears in the "TOML - GF Committed" column, and no other funding column has an entry for the project [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. The same row appears in the table in the September 2, 2026 agenda packet [2] Agenda (PDF), p. 52.
Why it matters
The table shows the project's carry-over amount placed in the General Fund-committed column [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Sources
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
- Agenda (PDF)
-
4 The project's amount differs across 2026 CIP tables: $125,000 in March and July, $200,000 in June, $215,000 in September
Updated
The Draft 2026-27 CIP Project List, filed with a March 3, 2026 meeting, includes the 2026 Townwide Striping Project [1] DRAFT 2026-27 CIP Project List.pdf, p. 1. The page text is too garbled to read an amount for it [1] DRAFT 2026-27 CIP Project List.pdf, p. 1.
The FY26-27 budget text filed with the June 17, 2026 meeting lists Total Budget FY26-27 of $200,000 [2] Final Budget Adoption FY26-27.pdf, p. 36.1. Table 1, "2026/27 CIP General Plan Conformance," in the July 8, 2026 agenda packet lists ST17 with a total of $125,000 [3] Agenda (PDF), p. 27.
Why it matters
A reader comparing them should note the document and date behind each figure [4] Agenda (PDF), p. 5[2] Final Budget Adoption FY26-27.pdf, p. 36.1[3] Agenda (PDF), p. 27[5] Agenda (PDF), p. 55.
Sources
- DRAFT 2026-27 CIP Project List.pdf
- Final Budget Adoption FY26-27.pdf
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
-
5 The budget text says the project is expected to be done by late spring 2026, but a September table still lists a carry-over
Updated
The FY26-27 budget text, filed with the June 17, 2026 meeting, says "The project is expected to be completed by late spring 2026" [1] Final Budget Adoption FY26-27.pdf, p. 36.1. The same sentence appears in the June 17, 2026 agenda packet [2] Agenda (PDF), p. 182.
The September 2, 2026 carry-over table lists the project in the CON phase with $215,000 carried from 25/26 to 26/27 [3] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Why it matters
The records give a spring 2026 completion expectation, yet a September table still lists a carry-over [1] Final Budget Adoption FY26-27.pdf, p. 36.1[3] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. They do not settle whether the work is finished [1] Final Budget Adoption FY26-27.pdf, p. 36.1[3] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Sources
- Final Budget Adoption FY26-27.pdf
- Agenda (PDF)
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
6 The CIP tables list the project as ST17 under Streets, with General Plan element M.7
Updated
Table 4 in the March 11, 2026 agenda packet lists "ST17 2026 Townwide Striping Project" under the Streets heading [1] Agenda (PDF), p. 5. Table 1, "2026/27 CIP General Plan Conformance," in the July 8, 2026 agenda packet lists ST17 with General Plan element M.7 [2] Agenda (PDF), p. 27.
Why it matters
The tables show the Town files the striping project under Streets and ties it to General Plan element M.7 [1] Agenda (PDF), p. 5[2] Agenda (PDF), p. 27.