Capital project
Annual Slurry and Striping Project (CIP ST4)
The project carries General Plan reference M.7 [1] Agenda (PDF), p. 27.
Updated
Findings
6 findings
-
1 The September 2026 outlook table lists $500,000 for the Annual Slurry and Striping Project (ST4) in FY2026-27, in the CON phase
Updated
The September 2, 2026 agenda packet's text does not show which column the figure sits in [1] Agenda (PDF), p. 53.
Why it matters
The table is labelled a CIP Budget Outlook, so the $500,000 is an outlook figure for FY2026-27 and not money spent [2] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.
Sources
- Agenda (PDF)
- Table 2 - CIP Budget Outlook for 26-27.pdf
-
2 The FY2026-27 $500,000 for ST4 moved from the "GF Uncommitted" column in the September 2025 outlook to "GF Committed" in the September 2026 outlook
Updated
The Table 2 - CIP Budget Outlook for 26/27, filed with the September 2, 2026 meeting, places the $500,000 in the "TOML - GF Committed" column [1] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1. The tables themselves give no reason for the change [2] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1[1] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.
Why it matters
The tables do not explain why [2] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1[1] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.
Sources
- Table 2 - CIP Budget Outlook for 26-27.pdf
- Table 3 - CIP Budget Outlook for 26-27.pdf
-
3 The September 2026 outlook table lists $500,000 for ST4 in FY2027-28, also under "GF Committed"
Updated
The September 2, 2026 agenda packet's text does not show which column the figure sits in [1] Agenda (PDF), p. 54.
Why it matters
Both entries are in the General Fund "Committed" column [2] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1[3] Table 3 - CIP Budget Outlook for 27-28.pdf, p. 1.
Sources
- Agenda (PDF)
- Table 2 - CIP Budget Outlook for 26-27.pdf
- Table 3 - CIP Budget Outlook for 27-28.pdf
-
4 ST4's five-year CIP total rose from $2,000,000 in the July 2026 packet to $2,500,000 in the September 2026 packet
Updated
Table 1 - 2026/27 CIP General Plan Conformance in the July 8, 2026 agenda packet shows the same [1] Agenda (PDF), p. 27.
The extracted text does not show which column each entry falls in [1] Agenda (PDF), p. 27[2] Agenda (PDF), p. 55.
Sources
- Agenda (PDF)
- Agenda (PDF)
-
5 ST4 carries General Plan reference M.7 in the CIP conformance tables
Updated
Table 1 - 2026/27 CIP General Plan Conformance in the July 8, 2026 agenda packet lists "ST4 M.7 Annual Slurry and Striping Project" in its "Gen Plan" column, under the "Streets" heading [1] Agenda (PDF), p. 27. Table 1 - 2025/26 CIP General Plan Conformance in the August 13, 2025 agenda packet also lists ST4 with M.7 [2] Agenda (PDF), p. 70.
Why it matters
The conformance tables tie ST4 to General Plan reference M.7, the same reference they give other street projects [1] Agenda (PDF), p. 27.
Sources
- Agenda (PDF)
- Agenda (PDF)
-
6 In 2021 CIP tables, project number ST4 was used for a differently named project, the 2024 Streets Rehabilitation Project
Updated
Both are 5-year tables for 21/22 through 25/26 [1] Agenda (PDF), p. 264[2] Agenda (PDF), p. 58.
Why it matters
Readers comparing years should match by name and not by number alone [1] Agenda (PDF), p. 264[3] Agenda (PDF), p. 70.
Sources
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)