Capital project
Parking at Parcel (50+ Spaces) (CIP TT9)
The Town's records describe TT9, "Parking at Parcel (50+ Spaces)", as a project to add about 50 parking spaces within the Parcel for residents' needs, not as a public lot, with a rough estimate of $150,000 [1] 2023-2024 Budget Book, p. 146.2[2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1.
Updated
Findings
7 findings
-
1 Latest CIP table, filed September 2026, lists TT9 in Construction with a $150,000 carry-over into FY2026-27
Updated
Table 1 - CIP Budget Outlook for 25/26 Carry Over to 26/27, filed with the September 2, 2026 meeting, lists "TT9 Parking at Parcel (50+ Spaces)" in the "CON" phase with $150,000 in the Totals column and $150,000 in the TOML - GF Committed column [1] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. The agenda packet page for the same table shows the same TT9 line [2] Agenda (PDF), p. 52.
Table 3 - CIP Budget Outlook for 26/27, filed with the September 3, 2025 meeting, lists TT9 in the "CON" phase with $150,000 in Totals and $150,000 in TOML - GF Uncommitted [3] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1. The agenda packet page for that table shows the same line [4] Agenda (PDF), p. 113.
Sources
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
- Agenda (PDF)
- Table 3 - CIP Budget Outlook for 26-27.pdf
- Agenda (PDF)
-
2 Town budget documents describe about 50 Parcel parking spaces for residents, not a public lot, with a $150,000 rough estimate
Updated
The FY2023-24 Budget Book says the spaces "are designed to meet specific needs of residents of the Parcel and is not intended as a public lot." [1] 2023-2024 Budget Book, p. 146.2
The 2023-2024 Budget Book gives the rough estimate for the project as $150,000 [1] 2023-2024 Budget Book, p. 146.2. The FY24-25 TOML Budget Book and the Fiscal Year 24-25 Final Budget page in the June 19, 2024 agenda packet repeat the description and the $150,000 estimate [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1[3] Agenda (PDF), p. 295.
The FY2023-24 Budget Book says the final location and design will be completed along with Phase II planning of the Parcel project [1] 2023-2024 Budget Book, p. 146.2. The FY24-25 documents say it will be completed along with Phase II and III planning [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1[3] Agenda (PDF), p. 295.
Why it matters
They also say the site's final location and design depend on Parcel planning phases [1] 2023-2024 Budget Book, p. 146.2[3] Agenda (PDF), p. 295.
Sources
- 2023-2024 Budget Book
- FY24-25 TOML BUDGET BOOK Web.pdf
- Agenda (PDF)
-
3 Budget documents recommend Gas Tax/Road Fund reserves, while CIP outlook tables list General Fund columns
Updated
The FY2023-24 Budget Book and the June 19, 2024 agenda packet each say "Funding is recommended from the Gas Tax/Road Fund reserves." [1] 2023-2024 Budget Book, p. 146.2[2] Agenda (PDF), p. 295 The June 15, 2022 agenda packet (Fiscal Year 22-23 Final Budget) lists "Budget of Road Fund Reserves for FY22-23: $150,000" [3] Agenda (PDF), p. 169.
A project list in the June 19, 2024 agenda packet (Fiscal Year 24-25 Final Budget, page 45) shows "Parking at Parcel (50+ Spaces)" under Transit and Mobility [4] Agenda (PDF), p. 270. It lists $150,000, Construction, and "Road Rehab Fund 210" [4] Agenda (PDF), p. 270. The FY24-25 documents give "Total Budget FY24-25: $150,000" [2] Agenda (PDF), p. 295[5] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1.
The CIP Budget Outlook tables place the $150,000 in TOML - GF Uncommitted for 24/25 and 26/27 and in TOML - GF Committed for 25/26 carry-over [6] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1[7] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1[8] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Why it matters
The narrative descriptions and the CIP outlook tables name different funding sources for the same $150,000 [2] Agenda (PDF), p. 295[6] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1.
Sources
- 2023-2024 Budget Book
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- FY24-25 TOML BUDGET BOOK Web.pdf
- Table 2 - CIP Budget Outlook for 24-25.pdf
- Table 3 - CIP Budget Outlook for 26-27.pdf
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
4 The $150,000 figure for TT9 appears in budget documents from FY2022-23 through FY2026-27
Updated
Table 2 - CIP Budget Outlook for 22/23, filed with the December 13, 2022 meeting, lists TT9 in the "CON" phase with a $150,000 total [1] Agenda (PDF), p. 17[2] Table 2 - CIP Budget Outlook for 22-23.pdf, p. 1. The July 20, 2022 agenda packet shows the same line [3] Agenda (PDF), p. 96.
The May 17, 2023 agenda packet and the Final Budget Adoption FY23-24 (filed with the June 21, 2023 meeting) both give "Carryover budget FY23-24: $150,000" [4] Agenda (PDF), p. 261[5] Final Budget Adoption FY23-24.pdf, p. 42.2. A table filed with the November 7, 2023 meeting, CIP Budget Outlook for 22/23 Carry Over to 23/24, lists TT9 in "CON" with $150,000 [6] Agenda (PDF), p. 86.
Table 2 - CIP Budget Outlook for 24/25, filed with the August 7, 2024 meeting, lists TT9 in "CON" with $150,000 [7] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1. A December 4, 2024 agenda packet page lists TT9 at $150,000 in the CIP Budget Outlook for 24/25 [8] Agenda (PDF), p. 191. The FY24-25 final budget pages give "Total Budget FY24-25: $150,000" [9] Agenda (PDF), p. 295[10] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1.
By our count, the figure is $150,000 in every one of these documents, so it did not change across FY2022-23, FY2023-24 and FY2024-25 [1] Agenda (PDF), p. 17[4] Agenda (PDF), p. 261[7] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1.
Why it matters
The same $150,000 has been carried through successive budget documents since FY2022-23, and the records show no other amount for this project in those outlook tables [1] Agenda (PDF), p. 17[7] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1[11] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Sources
- Agenda (PDF)
- Table 2 - CIP Budget Outlook for 22-23.pdf
- Agenda (PDF)
- Agenda (PDF)
- Final Budget Adoption FY23-24.pdf
- Agenda (PDF)
- Table 2 - CIP Budget Outlook for 24-25.pdf
- Agenda (PDF)
- Agenda (PDF)
- FY24-25 TOML BUDGET BOOK Web.pdf
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
5 Five-year CIP tables list $0 for TT9, unlike the budget outlook tables that list $150,000
Updated
The 2025/26 CIP General Plan Conformance table (August 13, 2025 packet) lists "TT9 M.7 Parking at Parcel (50+ Spaces)" with $0 [1] Agenda (PDF), p. 70. Table 4 - 25/26 5 year CIP (September 3, 2025 packet) lists TT9 with $0 [2] Agenda (PDF), p. 114. The Draft 2026/27 5-year CIP (March 3, 2026 packet), the 26/27 5 year CIP (March 11, 2026 packet) and its attached master project list also show TT9 at $0 [3] Agenda (PDF), p. 20[4] Agenda (PDF), p. 5[5] Draft 26-27 Master Project List.pdf, p. 1. The 2026/27 CIP General Plan Conformance table (July 8, 2026 packet) shows TT9 at $0 [6] Agenda (PDF), p. 27.
The 25/26 5-year CIP lists a different project, "TT7 Village Parking and Pedestrian Improvements - Pending Grant/Other Funding", at $1,000,000 [2] Agenda (PDF), p. 114. The same packets contain the budget outlook tables showing $150,000 for TT9 [7] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1[8] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Why it matters
A resident comparing CIP tables will see $0 for TT9 in the five-year lists and $150,000 in the budget outlook tables, so the table type matters when reading the figure [2] Agenda (PDF), p. 114[7] Table 3 - CIP Budget Outlook for 26-27.pdf, p. 1.
Sources
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Draft 26-27 Master Project List.pdf
- Agenda (PDF)
- Table 3 - CIP Budget Outlook for 26-27.pdf
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
6 The planned start for TT9 moved from FY22-23 to 2023 to FY23-24 in successive budget documents
Updated
The June 15, 2022 agenda packet (Fiscal Year 22-23 Final Budget) says "The work will be start in FY22-23" [1] Agenda (PDF), p. 169. The FY2023-24 Budget Book says "The work will begin in 2023." [2] 2023-2024 Budget Book, p. 146.2
The May 17, 2023 agenda packet and the Final Budget Adoption FY23-24 (filed with the June 21, 2023 meeting) say "The work is currently planned to start in FY23-24." [3] Agenda (PDF), p. 261[4] Final Budget Adoption FY23-24.pdf, p. 42.2 The FY24-25 documents quoted in this report give no start date [5] Agenda (PDF), p. 295[6] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.1.
Tables listing TT9 in the "CON" phase include the 22/23 outlook, the 22/23 carry-over to 23/24 outlook, the 26/27 outlook, and the 25/26 carry-over to 26/27 outlook [7] Agenda (PDF), p. 96[8] Agenda (PDF), p. 86[9] Agenda (PDF), p. 113[10] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Why it matters
Each budget cycle's documents restate the start timing for the same $150,000 project, and the records reviewed show no completion for it [1] Agenda (PDF), p. 169[3] Agenda (PDF), p. 261[10] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Sources
- Agenda (PDF)
- 2023-2024 Budget Book
- Agenda (PDF)
- Final Budget Adoption FY23-24.pdf
- Agenda (PDF)
- FY24-25 TOML BUDGET BOOK Web.pdf
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
7 In March 2022 the project first appeared in the five-year CIP as "GF15 Parking at Parcel (50+ Spaces)" with "XX" in place of dollar figures
Updated
Table 3 - 22/23 5 year CIP, in the March 16, 2022 agenda packet, lists "GF15 Parking at Parcel (50+ Spaces)" under General Facilities with "XX" in place of a dollar amount [1] Agenda (PDF), p. 38[2] Agenda (PDF), p. 39.
Sources
- Agenda (PDF)
- Agenda (PDF)