Downtown and Main Street

Town records trace Main Street planning from a 2010 district plan concept to the Main Street Plan accepted in February 2014, and to sidewalk segments finished in 2019. [1] Attachment A - Part 2, p. 84[2] Agenda Item 5, p. 11[3] 2019 Annual Planning Report and Attachments, p. 12 Capital budget tables list Main Street Landscaping at $715,000 and Old Mammoth Road Beautification at $500,000 in the 23/24 carry-over outlook, and the FY26-27 final budget narrative in the August 7, 2024 agenda packet lists $500,000 for Old Mammoth Road Beautification, with irrigation repaired in spring 2026. [4] Agenda (PDF), p. 65[5] Final Budget Adoption FY26-27.pdf, p. 41 Other records cover a 2022 EDA parking grant application near the Westin, the 2024 Civic Center bids, the Mammoth Lakes Foundation land purchase, and a proposed Old Mammoth Road hotel expansion. [6] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2[7] Award Construction Contract for the Town of Mammoth Lakes New Civic Center.pdf, p. 2[8] Final Budget Adoption FY26-27.pdf, p. 28[9] Agenda (PDF), p. 283

Updated

Findings

12 findings

  1. 1 Main Street Landscaping appears at $715,000 in a 2024 carry-over table, after a $335,000 staff estimate in 2021

    Updated

    A staff report filed with the October 20, 2021 meeting says Main Street Landscaping was identified in the 5-year CIP as a project slated for FY22-23 with no funding secured. [1] Staff Report(1).pdf, p. 3 Staff recommended that the $200,000 be allocated from fund balance to establish the project. [1] Staff Report(1).pdf, p. 3

    The CIP Budget Outlook for 22/23 in the December 13, 2022 agenda packet lists $250,000 for Main Street Landscaping (SS2). [2] Agenda (PDF), p. 17 The 22/23 5-year CIP in the July 20, 2022 agenda packet lists a total of $385,000 for the project. [3] Agenda (PDF), p. 98 The CIP Budget Outlook for 23/24 Carry Over to 24/25 lists a Project Total of $715,000 for SS2 Main Street Landscaping. [4] Agenda (PDF), p. 65 The December 4, 2024 agenda packet page that lists the same $715,000 summarizes planned FY24/25 projects. [5] Agenda (PDF), p. 190 The two figures come from different CIP tables, so this comparison is ours and not stated in the records. [2] Agenda (PDF), p. 17[4] Agenda (PDF), p. 65

    Why it matters

    The records give different figures at different stages: a $335,000 projected total cost in the 2021 staff report and a $715,000 project total in the 2024 carry-over outlook. [1] Staff Report(1).pdf, p. 3[4] Agenda (PDF), p. 65

    Sources

    1. Staff Report(1).pdf

      attachmentmeeting/filed datep. 3

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 17

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 98

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 65

    5. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 190

  2. 2 Old Mammoth Road Beautification has been planned since 2019 and is listed at $500,000 in the FY26-27 final budget document

    Updated

    The 2019 Annual Planning Report says construction was anticipated to begin in 2020. [1] 2019 Annual Planning Report and Attachments, p. 12

    The scope includes a new smart-technology drip irrigation system. [2] Agenda (PDF), p. 104

    The CIP Budget Outlook for 22/23 lists $500,000 for SS1. [3] Agenda (PDF), p. 17 The CIP Budget Outlook for 23/24 Carry Over to 24/25 lists a Project Total of $500,000. [4] Agenda (PDF), p. 65[5] Agenda (PDF), p. 190

    In spring 2026 the irrigation was dug up, repaired and tested, and plantings were expected when weather permits. [6] Final Budget Adoption FY26-27.pdf, p. 41

    Why it matters

    The FY26-27 final budget document reports significant progress expected in summer 2026. [6] Final Budget Adoption FY26-27.pdf, p. 41

    Sources

    1. 2019 Annual Planning Report and Attachments

      attachmentmeeting/filed datep. 12

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 104

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 17

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 65

    5. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 190

    6. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 41

  3. 3 The Main Street Plan was accepted by the Town Council in February 2014 after a 2010 district plan concept

    Updated

    The Downtown Neighborhood District Plan (Chapter 5, filed with the June 23, 2010 meeting) says most participants agreed the character and streetscape along Main Street needed significant improvement. [1] Attachment A - Part 2, p. 84 An implementation task in that plan, negotiating with Caltrans on the disposition of Main Street right-of-way, lists the Town and Caltrans as the parties. [2] Attachment A - Part 2, p. 114

    The Draft Main Street Plan was released in fall 2013, and the Final Plan was accepted by the Town Council and the PEDC in February 2014. [3] Agenda Item 5, p. 11

    A 2016 scope of services (Agenda Item 11, filed with the October 19, 2016 meeting) for the Downtown Mammoth Lakes revitalization process includes review of the Main Street Plan and the 2016 Hart Howerton Plan. [4] Agenda Item 11, p. 14 The Destination Resort Community and Economic Development Strategy update in the December 8, 2021 agenda packet says that during 2012-2021 the Town completed focused studies including the Main Street Plan and the Downtown Revitalization Plan. [5] Agenda (PDF), p. 25

    Sources

    1. Attachment A - Part 2

      attachmentmeeting/filed datep. 84

    2. Attachment A - Part 2

      attachmentmeeting/filed datep. 114

    3. Agenda Item 5

      attachmentmeeting/filed datep. 11

    4. Agenda Item 11

      attachmentmeeting/filed datep. 14

    5. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 25

  4. 4 The Main Street sidewalk project was concluded in 2019 with segments along the South Frontage Road and Sierra Boulevard to Mountain Boulevard

    Updated

    The other has no parallel parking on Main Street and maintains a 12-foot multi-use path. [1] Town Council — 2017-12-20, 1:42:39

    Why it matters

    The 2019 Annual Planning Report states the sidewalk project concluded in 2019 after openings in 2018. [2] 2019 Annual Planning Report and Attachments, p. 12

    Sources

    1. Town Council — 2017-12-20

      transcriptmeeting/filed date

    2. 2019 Annual Planning Report and Attachments

      attachmentmeeting/filed datep. 12

  5. 5 A $191,400 federal safety grant funds crosswalk beacon upgrades along Main Street (SR203)

    Updated

    The Capital Improvement Program Presentation says the grant funds upgrading two pedestrian-activated beacons (Laurel Mountain and Post Office) with RRFD signalization, and a third new RRFD beacon will be installed at Mountain Blvd. The project is along Main Street (SR203). [1] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2 The presentation lists an allocated budget of $191,400 for FY21-22 and a budget request of $50,000 for FY22-23, to come from SB1. [1] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    The CIP Budget Outlook for 22/23 lists TT8 SR203 (Main Street) Pedestrian Beacons (HSIP Grant) with $50,000 and $191,400 and a total of $241,400. [2] Agenda (PDF), p. 17 The 22/23 5-year CIP and its General Plan Consistency table each list a total of $241,400. [3] Agenda (PDF), p. 98[4] Agenda (PDF), p. 11

    Why it matters

    The records show a $191,400 grant plus $50,000 of SB1 funding, for a total of $241,400 for the Main Street beacon project. [1] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2[2] Agenda (PDF), p. 17

    Sources

    1. Capital Improvement Program Presentation 4-27-22.pdf

      attachmentmeeting/filed datep. 1.2

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 17

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 98

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 11

  6. 6 The Main Street South Side MUP Gap Closure (Town Loop) is listed at $250,000 in 2022 and $200,000 for plans in 2024-25 tables

    Updated

    The General Plan Consistency table in the July 13, 2022 packet also lists $250,000. [1] Agenda (PDF), p. 98[2] Agenda (PDF), p. 11

    A staff report filed with the December 3, 2024 meeting lists TR2 at $200,000, phase PS&E. [3] Staff Report(3).pdf, p. 3 The CIP Budget Outlook for 24/25 Carry Over to 25/26 in the September 3, 2025 agenda packet lists TR2 PS&E at $200,000. [4] Agenda (PDF), p. 111

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 98

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 11

    3. Staff Report(3).pdf

      attachmentmeeting/filed datep. 3

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 111

  7. 7 The Town applied for a $1 million EDA grant to add 20 parking spaces north of the Westin; the Town's 2022 presentation says a 25% match would be required

    Updated

    The Capital Improvement Program Presentation says the lot would include EV chargers and a path to the Westin stairs. [1] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    Why it matters

    The pages provided do not show whether the grant was awarded. [1] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    Sources

    1. Capital Improvement Program Presentation 4-27-22.pdf

      attachmentmeeting/filed datep. 1.2

  8. 8 Three bids were opened May 30, 2024 for the New Civic Center; the lowest base bid was $26,979,000

    Updated

    The Public Works Capital Project Update dated July 3, 2024 says the sale of bonds was complete and staff was requesting that the Town Council award the construction contract at that July 3 meeting. [1] Capital Project Update July 2024.7.3.pdf, p. 1 The CIP carry-over table in the September 3, 2025 packet lists GF14b Civic Center - Town Hall Construction (CON) at $29,500,000. [2] Agenda (PDF), p. 111

    The April 2022 presentation set out a FY22-23 budget request of $1,900,000 for Town Hall planning and design. [3] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    Sources

    1. Capital Project Update July 2024.7.3.pdf

      attachmentmeeting/filed datep. 1

    2. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 111

    3. Capital Improvement Program Presentation 4-27-22.pdf

      attachmentmeeting/filed datep. 1.2

  9. 9 The FY26-27 budget document says the Town bought Mammoth Lakes Foundation land for $4.5 million, with Measure U paying $180,000 a year toward the debt

    Updated

    Under the agreement, the Foundation would retain $1.5 million of the sale proceeds and donate $3.0 million to the construction of the MACC. [1] Final Budget Adoption FY26-27.pdf, p. 28 It says that, based on authorization from MLR in 2024, Measure U funds will contribute $180,000 annually to the debt service for the first 13 years. [1] Final Budget Adoption FY26-27.pdf, p. 28 The FY25-26 Final Budget contains the same figures. [2] FY25-26 Final Budget.pdf, p. 28

    The April 2022 presentation described the MACC location as property of about 8 acres owned by MLF. [3] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    Why it matters

    The budget documents tie the $4.5 million land cost to a $3.0 million Foundation donation toward the MACC and a 13-year Measure U contribution to debt service. [1] Final Budget Adoption FY26-27.pdf, p. 28

    Sources

    1. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 28

    2. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 28

    3. Capital Improvement Program Presentation 4-27-22.pdf

      attachmentmeeting/filed datep. 1.2

  10. 10 Measure U support for Edison Theater operations: $15,000 returned in FY25-26 and removed in FY26-27

    Updated

    The CIP Budget Outlook for 22/23 lists a total of $100,000 for Edison Theater Improvements (GF11). [1] Agenda (PDF), p. 17 The April 2022 presentation listed an option to reopen the Edison Theatre for programming in summer 2022. [2] Capital Improvement Program Presentation 4-27-22.pdf, p. 1.2

    Why it matters

    The budget documents tie the $15,000 Edison Theater support to the period of construction. [3] Final Budget Adoption FY26-27.pdf, p. 28[4] FY25-26 Final Budget.pdf, p. 28

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 17

    2. Capital Improvement Program Presentation 4-27-22.pdf

      attachmentmeeting/filed datep. 1.2

    3. Final Budget Adoption FY26-27.pdf

      attachmentmeeting/filed datep. 28

    4. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 28

  11. 11 An amended Phase One CSP for an Old Mammoth Road hotel site proposes 10 single-story resort cabins and 20 Villa units

    Updated

    The development standards table lists a 6.09-acre site, 149 existing hotel rooms, 20 Villa units and a maximum lot coverage of 70%. [1] Agenda (PDF), p. 283 The same table lists 'Number of additional new resort cabins rooms: 310 rooms'. [2] Attachment 4 - Resolution PEDC 2025-02.pdf, p. 19[1] Agenda (PDF), p. 283

    A resolution document dated December 11, 2024 says owner stays in the proposed condominium hotel units are limited to 30 days maximum per stay. [3] Attachment 1 - PEDC Resolution .pdf, p. 18

    Why it matters

    The documents describe the amendment as part of revitalizing the Old Mammoth Road corridor and animating its streetscape. [4] Agenda (PDF), p. 137[5] Agenda (PDF), p. 281

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 283

    2. Attachment 4 - Resolution PEDC 2025-02.pdf

      attachmentmeeting/filed datep. 19

    3. Attachment 1 - PEDC Resolution .pdf

      attachmentmeeting/filed datep. 18

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 137

    5. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 281

  12. 12 A January 2021 packet says the Town purchased The Parcel in 2018 as a near-term action under the 2017 Community Housing Action Plan

    Updated

    A document in the agenda packet filed with the January 6, 2021 meeting says the Community Housing Action Plan (CHAP), accepted by the Town Council in 2017, includes an objective to provide 200 to 300 community housing units within 5 years. [1] Agenda Packet, p. 385

    The Public Works Capital Project Update says Phase 2 'Kingfisher' includes 148 housing units. [2] Capital Project Update July 2024.7.3.pdf, p. 1

    Why it matters

    The July 2024 update is the latest status in the records provided. [1] Agenda Packet, p. 385[2] Capital Project Update July 2024.7.3.pdf, p. 1

    Sources

    1. Agenda Packet

      packetmeeting/filed datep. 385

    2. Capital Project Update July 2024.7.3.pdf

      attachmentmeeting/filed datep. 1