Capital project
Parcel Infrastructure Grant (CIP AF4)
The Town and its Parcel Development Partner, Pacific West Communities, were awarded a $20.6 million Infill Infrastructure Grant from the California Department of Housing and Community Development [1] FY25-26 Final Budget.pdf, p. 34[2] Final Budget Adoption FY23-24.pdf, p. 42. It pays for public and private infrastructure for an affordable housing project planned for a minimum of 450 units [1] FY25-26 Final Budget.pdf, p. 34[2] Final Budget Adoption FY23-24.pdf, p. 42. Budget documents from 2022 and 2023 describe Phase I (81 units) as under construction and Phase II as in the approval process [2] Final Budget Adoption FY23-24.pdf, p. 42[3] Agenda (PDF), p. 246[4] Restricted Revenue capital and Housing fy25-26.pdf, p. 7. A document filed with the May 21, 2025 meeting says the Town would keep working on the initial 76 units of Phase 2 and on planning for Phase 3 [2] Final Budget Adoption FY23-24.pdf, p. 42[3] Agenda (PDF), p. 246[4] Restricted Revenue capital and Housing fy25-26.pdf, p. 7. Capital budget tables carry $11,000,000 for the AF4 project from FY2023-24 through the 24/25-to-25/26 carry-over, while the FY2024-25 and FY2025-26 budget narratives list the total budget as TBD [2] Final Budget Adoption FY23-24.pdf, p. 42[5] Agenda (PDF), p. 111[6] Final Budget Adoption FY24-25.pdf, p. 45[1] FY25-26 Final Budget.pdf, p. 34.
Updated
Findings
8 findings
-
1 The state awarded the Town and Pacific West Communities a $20.6 million Infill Infrastructure Grant for the Parcel affordable housing project
Updated
The FY25-26 Final Budget says the Town and the Parcel Development Partner (Pacific West Communities) were awarded a $20.6 million Infill Infrastructure Grant (IIG) from the California Department of Housing and Community Development [1] FY25-26 Final Budget.pdf, p. 34. It says the funds will be used over several years as the Parcel is built out, for public and private infrastructure supporting this affordable housing project, and that build out is planned to include a minimum of 450 housing units [1] FY25-26 Final Budget.pdf, p. 34. The same description appears in the FY23-24 Final Budget Adoption, the 2023-2024 Budget Book, the 2022-2023 Council Adopted Budget, the FY24-25 Final Budget page in the June 19, 2024 agenda packet, and the April 27, 2022 agenda packet [2] Final Budget Adoption FY23-24.pdf, p. 42[3] 2023-2024 Budget Book, p. 146[4] 2022-2023 Council Adopted Budget, p. 35[5] Agenda (PDF), p. 273[6] Agenda (PDF), p. 43.
The April 27, 2022 summary chart lists "Total State Grant Award $20.6M" for the Parcel Infrastructure Grant (IIG) [7] Agenda (PDF), p. 56. The 2021/22 Capital Improvement Plan page in the September 8, 2021 agenda packet says the Town and the Pacific Companies were awarded $20,601,216 during the fiscal year 19/20 grant cycle [8] Agenda (PDF), p. 80. It says the funding would support first-phase infrastructure and the parking podium [8] Agenda (PDF), p. 80. The FY25-26 Final Budget says the capital budget carries the grant funding over time and that actual use of the funds will depend on construction schedules [1] FY25-26 Final Budget.pdf, p. 34.
Why it matters
The budget documents describe the grant as paying for infrastructure for a housing project planned at a minimum of 450 units, and they say the timing of spending depends on construction schedules [1] FY25-26 Final Budget.pdf, p. 34[2] Final Budget Adoption FY23-24.pdf, p. 42.
Sources
- FY25-26 Final Budget.pdf
- Final Budget Adoption FY23-24.pdf
- 2023-2024 Budget Book
- 2022-2023 Council Adopted Budget
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
-
2 Budget documents say Phase 1 grant funds covered parking podiums, underground infrastructure and street work
Updated
The FY25-26 Final Budget says that for Phase 1 of the Parcel the grant funds covered the parking podiums of both buildings, underground infrastructure, the extension of Tavern Road, integration of infrastructure on Laurel Mountain Road, and Inyo Street [1] FY25-26 Final Budget.pdf, p. 34. The 2024-2025 Budget Book, the FY24-25 Final Budget page and the Restricted Revenue capital and Housing fy25-26 document filed with the May 21, 2025 meeting give the same Phase 1 scope [2] 2024-2025 Budget Book, p. 163[3] Agenda (PDF), p. 273[4] Restricted Revenue capital and Housing fy25-26.pdf, p. 7.
The 2021/22 Capital Improvement Plan page in the September 8, 2021 agenda packet describes the infrastructure planned for the project [5] Agenda (PDF), p. 80. The Agenda (PDF) says the Town and Pacific Companies intended to begin construction in Fall of 2021 [5] Agenda (PDF), p. 80.
Why it matters
The records show the grant paying for both building-related infrastructure and public street work [1] FY25-26 Final Budget.pdf, p. 34.
Sources
- FY25-26 Final Budget.pdf
- 2024-2025 Budget Book
- Agenda (PDF)
- Restricted Revenue capital and Housing fy25-26.pdf
- Agenda (PDF)
-
3 Budget documents described Phase I (81 units) as under construction and Phase II as in approval; a 2025 document points to Phase 2 and Phase 3 work
Updated
The April 27, 2022 agenda packet, the 2022-2023 Council Adopted Budget and the June 15, 2022 agenda packet each say Phase I (81 units) is under construction and Phase II is in the approval process [1] Agenda (PDF), p. 43[2] 2022-2023 Council Adopted Budget, p. 35[3] Agenda (PDF), p. 153. The April 2022 packet described Phase II as approximately 141 units [1] Agenda (PDF), p. 43. The June 2022 packet described Phase 2 (AF7) as 146 affordable units plus 2 manager units, 148 total units [3] Agenda (PDF), p. 153.
The May 17, 2023 agenda packet and the FY23-24 Final Budget Adoption say Phase I (81 units) is under construction and Phase II (148 units in two phases) is in the approval phase [4] Agenda (PDF), p. 246[5] Final Budget Adoption FY23-24.pdf, p. 42[6] Fund 245 and 300.pdf, p. 14. The 2023-2024 Budget Book says Phase I is under construction and Phase II is in the approval process [7] 2023-2024 Budget Book, p. 146.
The FY24-25 and FY25-26 budget pages use the past tense for Phase 1, saying the grant funds "covered" its infrastructure [8] Agenda (PDF), p. 273[9] FY25-26 Final Budget.pdf, p. 34. The Restricted Revenue capital and Housing fy25-26 document filed with the May 21, 2025 meeting is the latest status in these records [10] Restricted Revenue capital and Housing fy25-26.pdf, p. 7. It lists housing work to continue in the upcoming year: development of the initial 76 units in Phase 2 of the Parcel (Kingfisher 2.1), planning for Phase 3 (ownership phase) with potential site work in spring 2026, and planning for the remaining phases [10] Restricted Revenue capital and Housing fy25-26.pdf, p. 7.
Why it matters
Unit counts and statuses are those stated in each document at its date [5] Final Budget Adoption FY23-24.pdf, p. 42[10] Restricted Revenue capital and Housing fy25-26.pdf, p. 7.
Sources
- Agenda (PDF)
- 2022-2023 Council Adopted Budget
- Agenda (PDF)
- Agenda (PDF)
- Final Budget Adoption FY23-24.pdf
- Fund 245 and 300.pdf
- 2023-2024 Budget Book
- Agenda (PDF)
- FY25-26 Final Budget.pdf
- Restricted Revenue capital and Housing fy25-26.pdf
-
4 Early budgets set $7.5 million for FY2021-22 and $3.5 million for FY2022-23, an $11 million commitment
Updated
The 5-Year CIP in the September 8, 2021 agenda packet lists $7,500,000 for 21/22, $3,500,000 for 22/23, $3,000,000 each for 23/24, 24/25 and 25/26, and a $20,000,000 total [1] Agenda (PDF), p. 80. The Agenda (PDF) shows a total funding commitment of $11,000,000, with the revenue source listed as "Carryover / New Allocation" [2] Agenda (PDF), p. 56. By our calculation, $7,500,000 plus $3,500,000 equals $11,000,000 [2] Agenda (PDF), p. 56.
The 2022-2023 Council Adopted Budget and the June 15, 2022 agenda packet list a Carryover Budget FY21-22 of $7,500,000 and a Budget Allocation FY22-23 of $3,500,000 [3] 2022-2023 Council Adopted Budget, p. 35[4] Agenda (PDF), p. 153. They say the FY21-22 budget allocated $7.5 million with remaining funds extending out over the 5-year capital plan [3] 2022-2023 Council Adopted Budget, p. 35[4] Agenda (PDF), p. 153. Agenda packets from December 2022 list AF4 at $7,500,000 in the 21/22 carry-over outlook and $3,500,000 in the 22/23 outlook [5] Agenda (PDF), p. 16[6] Agenda (PDF), p. 17.
Why it matters
They show how much the Town's capital plans set aside for the project in the first two fiscal years [3] 2022-2023 Council Adopted Budget, p. 35[2] Agenda (PDF), p. 56.
Sources
- Agenda (PDF)
- Agenda (PDF)
- 2022-2023 Council Adopted Budget
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
-
5 Capital budget tables carry $11,000,000 for the AF4 project from FY2023-24 into the 24/25-to-25/26 carry-over
Updated
The FY23-24 Final Budget Adoption, the 2023-2024 Budget Book and the May 17, 2023 agenda packet list a Total Carryover Budget Allocation FY23-24 of $11,000,000 for the Parcel Infrastructure Grant (AF4) [1] Final Budget Adoption FY23-24.pdf, p. 42[2] 2023-2024 Budget Book, p. 146[3] Agenda (PDF), p. 246. Later tables list AF4 IIG Parcel Infrastructure (Town Infrastructure) in the Construction (CON) phase with a project total of $11,000,000 in each of these: - the November 7, 2023 agenda packet's Table 1, CIP Budget Outlook for 22/23 Carry Over to 23/24 [4] Agenda (PDF), p. 86; - the 2024-2025 Budget Book's outlook for 23/24 Carry Over to 24/25 [5] 2024-2025 Budget Book, p. 161; - the August 7, 2024 agenda packet's Table 1 [6] Agenda (PDF), p. 65[7] Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf, p. 1; - the report on 2024/25 & 2025/26 Carry-Over CIP Projects filed with the December 18, 2024 meeting [8] Town Council Staff Report_2025 Strategic Planning Series_V4_12-18-2024PK.pdf, p. 3; - the September 3, 2025 agenda packet's outlook for 24/25 Carry Over to 25/26 [9] Agenda (PDF), p. 111.
The FY2024-25 Capital Projects Budget Highlights in a December 4, 2024 agenda packet also list the project at $11,000,000 [10] Agenda (PDF), p. 190. A staff report filed with the December 3, 2024 meeting lists AF4 at $11,000,000 in the CON phase [11] Staff Report(3).pdf, p. 3.
Why it matters
The same $11,000,000 appears as the carried-over budget for this project in each year's carry-over table through the 24/25-to-25/26 outlook [4] Agenda (PDF), p. 86[9] Agenda (PDF), p. 111. These are budget figures, not money spent [4] Agenda (PDF), p. 86[9] Agenda (PDF), p. 111.
Sources
- Final Budget Adoption FY23-24.pdf
- 2023-2024 Budget Book
- Agenda (PDF)
- Agenda (PDF)
- 2024-2025 Budget Book
- Agenda (PDF)
- Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf
- Town Council Staff Report_2025 Strategic Planning Series_V4_12-18-2024PK.pdf
- Agenda (PDF)
- Agenda (PDF)
- Staff Report(3).pdf
-
6 The FY2024-25 and FY2025-26 budget narratives list the total budget for the Parcel Infrastructure Grant as TBD
Updated
The FY24-25 Final Budget Adoption lists "Total Budget FY24-25: TBD with Phase 2 of the Parcel project" [1] Final Budget Adoption FY24-25.pdf, p. 45. The 2024-2025 Budget Book and the FY24-25 Final Budget page in the June 19, 2024 agenda packet say the same [2] 2024-2025 Budget Book, p. 163[3] Agenda (PDF), p. 273. The FY25-26 Final Budget lists "Total Budget FY25-26 TBD with future phases of the Parcel" [4] FY25-26 Final Budget.pdf, p. 34. The Restricted Revenue capital and Housing fy25-26 document lists IIG Parcel Infrastructure (Town Infrastructure) as TBD for FY25-26 [5] Restricted Revenue capital and Housing fy25-26.pdf, p. 7.
Why it matters
These budget narratives give no dollar total for FY2024-25 or FY2025-26, even though carry-over tables list $11,000,000 [4] FY25-26 Final Budget.pdf, p. 34[6] Agenda (PDF), p. 111. The pages do not explain how the two relate [4] FY25-26 Final Budget.pdf, p. 34[6] Agenda (PDF), p. 111.
Sources
- Final Budget Adoption FY24-25.pdf
- 2024-2025 Budget Book
- Agenda (PDF)
- FY25-26 Final Budget.pdf
- Restricted Revenue capital and Housing fy25-26.pdf
- Agenda (PDF)
-
7 Pages disagree on the project's FY2023-24 outlook amount: $3,000,000 on some, blank on others
Updated
The July 20, 2022, November 1, 2022 and December 13, 2022 agenda packets each list AF4 IIG Parcel Infrastructure (Town Infrastructure), in the CON phase, with a total of $3,000,000 in Table 3 - CIP Budget Outlook for 23/24 [1] Agenda (PDF), p. 97[2] Agenda (PDF), p. 44[3] Agenda (PDF), p. 18. That matches the $3,000,000 shown for 23/24 in the 2021 5-Year CIP [4] Agenda (PDF), p. 80.
The separate Table 3 attachments filed with the July 20, 2022 and December 13, 2022 meetings show the AF4 row with no amount [5] Table 3 - CIP Budget Outlook for 23-24.pdf, p. 1[6] Table 3 - CIP Budget Outlook for 23-24.pdf, p. 1. The 2023-2024 Budget Book's 22/23 CIP Carry Over to 23/24 table also shows no amount in the AF4 row [7] 2023-2024 Budget Book, p. 144. By contrast, the Budget Book narrative and the November 2023 Table 1 list $11,000,000 for the project [8] 2023-2024 Budget Book, p. 146[9] Agenda (PDF), p. 86.
Why it matters
The FY2023-24 outlook amount for this project is shown as $3,000,000 on some pages and left blank on others, so the pages do not agree on it [1] Agenda (PDF), p. 97[6] Table 3 - CIP Budget Outlook for 23-24.pdf, p. 1.
Sources
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Agenda (PDF)
- Table 3 - CIP Budget Outlook for 23-24.pdf
- Table 3 - CIP Budget Outlook for 23-24.pdf
- 2023-2024 Budget Book
- 2023-2024 Budget Book
- Agenda (PDF)
-
8 A resident's April 2022 public comment letter urged the Town to keep relying on its partnership with Pacific
Updated
Grady Dutton submitted a public comment letter for the Town Council Special Meeting of April 27, 2022, Item 4.2, Preliminary Capital Improvement Program Project and Budgets [1] Grady Dutton Public Comment.pdf, p. 1. He wrote that the Town needs to continue to rely on its partnership [1] Grady Dutton Public Comment.pdf, p. 1.
Why it matters
The document filed with the April 27, 2022 meeting shows that at least one commenter weighed in on the grant during the April 27, 2022 budget discussion [1] Grady Dutton Public Comment.pdf, p. 1.
Sources
- Grady Dutton Public Comment.pdf