Reconstruct Town-Hangar Taxilanes Design (CIP AP4)

The Table 2 CIP Budget Outlook lists $150,000 for FY2024-25, $229,000 for FY2025-26 and $235,500 for FY2026-27 [1] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1[2] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1[3] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1. Budget documents from 2024 and 2025 say the design would be completed in FY 24/25 in preparation for 2025 construction [4] Agenda (PDF), p. 279[5] FY25-26 Final Budget.pdf, p. 34. The outlook for 26/27 lists the AP4a project in the CON (construction) phase, funded from the FAA column [3] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

Updated

Findings

5 findings

  1. 1 Taxilane design budget figure rose from $150,000 (FY2024-25) to $229,000 (FY2025-26) to $235,500 in the FY2026-27 outlook

    Updated

    The Table 2 CIP Budget Outlook for 24/25, filed with the August 7, 2024 meeting, lists AP4a Reconstruct Town-Hangar Taxilanes Design in phase PS&E with a total of $150,000 [1] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1. The FY24-25 Town budget book likewise gives "Total Budget FY24-25 Design: $150,000" [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.

    The FY25-26 Final Budget gives "Total Budget FY25-26 Design: $229,000" for the Town Hangar Taxilane Reconstruction - Design (AP4a) [3] FY25-26 Final Budget.pdf, p. 34[4] Agenda (PDF), p. 106. The Table 2 CIP Budget Outlook for 25/26, filed with the September 3, 2025 meeting, lists AP4a in phase PS&E with a total of $229,000 [5] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1. A May 2025 agenda packet also lists $229,000 for Reconstruct Town-Hangar Taxilanes Design in the Fiscal Year 25-26 Budget – Capital, Housing & Restricted Funds document [6] Agenda (PDF), p. 64.

    The Table 2 CIP Budget Outlook for 26/27, filed with the September 2, 2026 meeting, lists AP4a in phase CON with a total of $235,500 [7] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1. The September 2, 2026 agenda packet shows the same line [8] Agenda (PDF), p. 53.

    By our calculation, the figure rose by $79,000 (+52.7%) from FY2024-25 to FY2025-26 and by $6,500 (+2.8%) from FY2025-26 to FY2026-27 [1] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1[5] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1[7] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Why it matters

    The three outlook tables show the project's budget figure and its phase label (PS&E, then CON) changing from one fiscal year to the next [1] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1[5] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1[7] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Sources

    1. Table 2 - CIP Budget Outlook for 24-25.pdf

      attachmentmeeting/filed datep. 1

    2. FY24-25 TOML BUDGET BOOK Web.pdf

      attachmentmeeting/filed datep. 165

    3. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 106

    5. Table 2 - CIP Budget Outlook for 25-26.pdf

      attachmentmeeting/filed datep. 1

    6. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 64

    7. Table 2 - CIP Budget Outlook for 26-27.pdf

      attachmentmeeting/filed datep. 1

    8. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 53

  2. 2 Budget documents said design would finish in FY 24/25 for 2025 construction; the 25/26 outlook still lists PS&E and the 26/27 outlook lists CON

    Updated

    The FY24-25 Final Budget page in the June 19, 2024 agenda packet says the design "will be completed in FY 24/25 in preparation for 2025 construction" [1] Agenda (PDF), p. 279. The FY24-25 Town budget book says the same [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.

    A May 2025 agenda packet and the FY25-26 Final Budget repeat that sentence [3] Agenda (PDF), p. 66[4] FY25-26 Final Budget.pdf, p. 34. The Restricted Revenue capital and Housing fy25-26 document filed with the May 21, 2025 meeting also repeats it [5] Restricted Revenue capital and Housing fy25-26.pdf, p. 7.

    The Table 2 outlook for 25/26 lists AP4a in phase PS&E [6] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1. The Table 2 outlook for 26/27 lists it in phase CON [7] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Why it matters

    Residents can see the planned schedule in the 2024 and 2025 budget text alongside the phase labels in the later outlook tables [4] FY25-26 Final Budget.pdf, p. 34[6] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1[7] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 279

    2. FY24-25 TOML BUDGET BOOK Web.pdf

      attachmentmeeting/filed datep. 165

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 66

    4. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34

    5. Restricted Revenue capital and Housing fy25-26.pdf

      attachmentmeeting/filed datep. 7

    6. Table 2 - CIP Budget Outlook for 25-26.pdf

      attachmentmeeting/filed datep. 1

    7. Table 2 - CIP Budget Outlook for 26-27.pdf

      attachmentmeeting/filed datep. 1

  3. 3 Funding sources shift across years: Town funds until a 2025 Airport Improvement Grant submission, then grant and FAA columns

    Updated

    The June 2024 FY24-25 Final Budget page and the FY24-25 budget book say the design "will be funded with Town funding, until an Airport Improvement Grant (AIG) is submitted in 2025 to reimburse the design costs" [1] Agenda (PDF), p. 279[2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165. The Final Budget Adoption FY24-25 table, filed with the June 19, 2024 meeting, lists the funding source for Town Hangar Taxilane Reconstruction as "FAA AIG Grant and TOML Funds" [3] Final Budget Adoption FY24-25.pdf, p. 44.

    The May 2025 packet and the FY25-26 Final Budget use the past tense: an AIG "was submitted in 2025 to reimburse the design costs" [4] Agenda (PDF), p. 66[5] FY25-26 Final Budget.pdf, p. 34.

    The 24/25 outlook table places the $150,000 in its Grants / Donations column [6] Table 2 - CIP Budget Outlook for 24-25.pdf, p. 1. The 25/26 outlook table splits the $229,000 into $21,389 under TOML - GF Committed M - U and $207,611 under Grants [7] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1. By our calculation, those two amounts sum to $229,000 [8] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Why it matters

    The records show how the project's stated funding changed between fiscal years, from Town funding with a planned grant reimbursement to grant and FAA columns [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165[7] Table 2 - CIP Budget Outlook for 25-26.pdf, p. 1[8] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1.

    Sources

    1. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 279

    2. FY24-25 TOML BUDGET BOOK Web.pdf

      attachmentmeeting/filed datep. 165

    3. Final Budget Adoption FY24-25.pdf

      attachmentmeeting/filed datep. 44

    4. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 66

    5. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34

    6. Table 2 - CIP Budget Outlook for 24-25.pdf

      attachmentmeeting/filed datep. 1

    7. Table 2 - CIP Budget Outlook for 25-26.pdf

      attachmentmeeting/filed datep. 1

    8. Table 2 - CIP Budget Outlook for 26-27.pdf

      attachmentmeeting/filed datep. 1

  4. 4 Design covers three taxilanes between the Town Hangars, with full-depth reconstruction and drainage grading

    Updated

    The FY25-26 Final Budget says three taxilanes are located between the Town Hangars at Mammoth Yosemite Airport [1] FY25-26 Final Budget.pdf, p. 34. The FY24-25 budget book says the taxilane asphalt "has deteriorated greatly and has an extremely low Pavement Condition Index" [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165. The proposed design "will include full-depth reconstruction of the taxilanes and minor grading improvements to fix existing drainage issues" [1] FY25-26 Final Budget.pdf, p. 34[3] Agenda (PDF), p. 66.

    Why it matters

    The budget text states the pavement condition and the reconstruction scope that the design budget covers [2] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165[1] FY25-26 Final Budget.pdf, p. 34.

    Sources

    1. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34

    2. FY24-25 TOML BUDGET BOOK Web.pdf

      attachmentmeeting/filed datep. 165

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 66

  5. 5 The Town issued a 2023 Request for Qualifications for engineering of multiple airport projects, including this one

    Updated

    The FY25-26 Final Budget says "In 2023 the Town issued a Request for Qualifications (RFQ) for engineering of multiple projects at the Airport including this project" [1] FY25-26 Final Budget.pdf, p. 34[2] FY25-26 Final Budget.pdf, p. 35. The June 2024 FY24-25 Final Budget page and the FY24-25 budget book contain the same statement [3] Agenda (PDF), p. 279[4] FY24-25 TOML BUDGET BOOK Web.pdf, p. 165.

    Why it matters

    The budget text identifies the 2023 engineering solicitation that covered this project among several airport projects [1] FY25-26 Final Budget.pdf, p. 34[3] Agenda (PDF), p. 279.

    Sources

    1. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 34

    2. FY25-26 Final Budget.pdf

      attachmentmeeting/filed datep. 35

    3. Agenda (PDF)

      agenda_pdfmeeting/filed datep. 279

    4. FY24-25 TOML BUDGET BOOK Web.pdf

      attachmentmeeting/filed datep. 165