Capital project
Park Signage (CIP PR16)
The Fiscal Year 26-27 Final Budget lists a Total Budget FY26-27 of $100,000 for Park Signage (PR16) [1] Final Budget Adoption FY26-27.pdf, p. 36[2] Final Budget Adoption FY26-27.pdf, p. 41. The money is for three new park monument signs at Mammoth Creek Park West, the Dog Park and Shady Rest Park, and the document says work will begin in summer 2026 [1] Final Budget Adoption FY26-27.pdf, p. 36[2] Final Budget Adoption FY26-27.pdf, p. 41. The same $100,000 appears as carried over from FY2025-26, when the FY25-26 budget text had work starting in summer 2025 [3] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[4] FY25-26 Final Budget.pdf, p. 34. The FY26-27 text adds that the contract will be combined with TBID signage and some informational signs at Mammoth Creek Park [2] Final Budget Adoption FY26-27.pdf, p. 41.
Updated
Findings
6 findings
-
1 FY26-27 Final Budget lists $100,000 for three new park monument signs
Updated
The Fiscal Year 26-27 Final Budget (the "Final Budget Adoption FY26-27" file, filed with the June 17, 2026 meeting) says funding "was set aside to construct three new park monument signs [1] Final Budget Adoption FY26-27.pdf, p. 36[2] Final Budget Adoption FY26-27.pdf, p. 41." The Final Budget Adoption FY26-27 lists "Total Budget FY26-27 $100,000" [1] Final Budget Adoption FY26-27.pdf, p. 36[2] Final Budget Adoption FY26-27.pdf, p. 41.
The Tentative Budget FY26-27 (filed with the June 3, 2026 meeting) and the June 17, 2026 agenda packet carry the same text and the same $100,000 figure [3] Tentative Budget FY26-27.pdf, p. 17[4] Agenda (PDF), p. 178.
The FY25-26 Final Budget (filed with the June 18, 2025 meeting) lists "Total Budget FY25-26 $100,000" for Park Signage (PR16), with the same three locations [5] FY25-26 Final Budget.pdf, p. 34. The Restricted Revenue, Capital and Housing FY25-26 document (filed with the May 21, 2025 meeting) also lists Park Signage at $100,000 [6] Restricted Revenue capital and Housing fy25-26.pdf, p. 7. By our comparison, the Total Budget figure is $100,000 in both FY2025-26 and FY2026-27 [5] FY25-26 Final Budget.pdf, p. 34[1] Final Budget Adoption FY26-27.pdf, p. 36.
Why it matters
These budget documents set out what the $100,000 for Park Signage (PR16) is meant to build and where the signs are to go [1] Final Budget Adoption FY26-27.pdf, p. 36. The figure is a budget amount, not spending [1] Final Budget Adoption FY26-27.pdf, p. 36.
Sources
- Final Budget Adoption FY26-27.pdf
- Final Budget Adoption FY26-27.pdf
- Tentative Budget FY26-27.pdf
- Agenda (PDF)
- FY25-26 Final Budget.pdf
- Restricted Revenue capital and Housing fy25-26.pdf
-
2 FY26-27 budget text says work begins summer 2026 and the contract will be combined with TBID signage
Updated
The FY26-27 Final Budget says: "Work will begin in summer 2026 [1] Final Budget Adoption FY26-27.pdf, p. 41. The contract will be combined with the TBID signage and some informational signs at Mammoth Creek Park" [1] Final Budget Adoption FY26-27.pdf, p. 41. The Tentative Budget FY26-27 and the June 17, 2026 agenda packet contain the same sentences [2] Tentative Budget FY26-27.pdf, p. 17[3] Agenda (PDF), p. 178.
The FY25-26 Final Budget said "Work will begin in summer 2025" for the same project [4] FY25-26 Final Budget.pdf, p. 34. The FY25-26 Restricted Revenue, Capital and Housing document and the May 21, 2025 agenda packet say the same [5] Restricted Revenue capital and Housing fy25-26.pdf, p. 7[6] Agenda (PDF), p. 70. The FY25-26 Final Budget text for Park Signage does not mention TBID signage [4] FY25-26 Final Budget.pdf, p. 34.
Why it matters
The two budget documents give different work-start seasons for the same project: summer 2025 in the FY25-26 budget and summer 2026 in the FY26-27 budget [4] FY25-26 Final Budget.pdf, p. 34[1] Final Budget Adoption FY26-27.pdf, p. 41.
Sources
- Final Budget Adoption FY26-27.pdf
- Tentative Budget FY26-27.pdf
- Agenda (PDF)
- FY25-26 Final Budget.pdf
- Restricted Revenue capital and Housing fy25-26.pdf
- Agenda (PDF)
-
3 Town tables show Park Signage's $100,000 carried over into FY2026-27
Updated
Table 4 - 26/27 5-year CIP (filed with the same meeting) reads Park Signage with $100,000 in the previous & carryover column and $100,000 as the total [1] Table 4 - 26-27 5-year CIP.pdf, p. 1. The table text is jumbled in the extraction, so the column placement is our reading [1] Table 4 - 26-27 5-year CIP.pdf, p. 1.
The 25/26 5-year CIP table (filed with the September 3, 2025 meeting) shows Park Signage with $100,000 under previous & carryover and a $100,000 total [2] Table 4 – 25-26 5-year CIP.pdf, p. 1. The "CIP Budget Outlook for 24/25 Carry Over to 25/26" lists PR16 Park Signage (CON) at $100,000, in the "M - R" column as the cells read [3] Table 1 - CIP Budget Outlook for 24-25 Carry Over.pdf, p. 1. The "CIP Budget Outlook for 23/24 Carry Over to 24/25" (filed with the August 7, 2024 meeting) lists PR16 Park Signage (CON) at $100,000, also in the "M - R" column as the cells read [4] Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf, p. 1. By our reading of these tables, the funding-source column changed from M - R to TOML - GF Committed between the 24/25 and 25/26 outlooks [3] Table 1 - CIP Budget Outlook for 24-25 Carry Over.pdf, p. 1[5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
Sources
- Table 4 - 26-27 5-year CIP.pdf
- Table 4 – 25-26 5-year CIP.pdf
- Table 1 - CIP Budget Outlook for 24-25 Carry Over.pdf
- Table 1 - CIP Budget Outlook for 23-24 Carry Over .pdf
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
-
4 Planned sign locations changed between the 2024 recommendation and the FY25-26 and FY26-27 budgets
Updated
The 3rd Qtr FY22-23 says the signs "will be located at the Community Recreation Center, Park at the Parcel, and the dog park" [1] 3rd Qtr FY22-23.pdf, p. 3.
At the Town Council's March 19, 2025 meeting, a presenter said at 01:36:55 in the recording: "Our park signage, this was approved a year or so ago [2] Town Council — 2025-03-19 15:00:00, 1:28:51. These are monument signs at three of our parks" [2] Town Council — 2025-03-19 15:00:00, 1:28:51.
The FY25-26 Final Budget names Mammoth Creek Park West, Dog Park, and Shady Rest Park [3] FY25-26 Final Budget.pdf, p. 34. The FY26-27 Final Budget names Mammoth Creek Park West, the Dog Park, and Shady Rest Park [4] Final Budget Adoption FY26-27.pdf, p. 36.
Why it matters
The project's stated locations differ between the 2024 document and the FY25-26 and FY26-27 budget documents [1] 3rd Qtr FY22-23.pdf, p. 3[3] FY25-26 Final Budget.pdf, p. 34[4] Final Budget Adoption FY26-27.pdf, p. 36.
Sources
- 3rd Qtr FY22-23.pdf
- Town Council — 2025-03-19 15:00:00
- FY25-26 Final Budget.pdf
- Final Budget Adoption FY26-27.pdf
-
5 March 2026 Parks Commission staff report says Outdoor Recreation office is managing the signage program
Updated
A Parks and Recreation Commission staff report (filed with the March 3, 2026 meeting) has a section "PR 16 - Park Signage [1] Staff Report.pdf, p. 6[2] Agenda (PDF), p. 15." The Staff Report continues: "The Office of Outdoor Recreation is managing this program to maintain consistency with Town-wide existing signage and wayfinding" [1] Staff Report.pdf, p. 6[2] Agenda (PDF), p. 15.
The report adds: "In addition to these larger signs illustrated below, staff are working to install informational and safety signage on the new prefabricated climbing boulder at Mammoth Creek Park" [1] Staff Report.pdf, p. 6[2] Agenda (PDF), p. 15. The report's table lists PR16 Park Signage at $100,000 [1] Staff Report.pdf, p. 6.
Why it matters
This staff report names the Town office managing the signage program and says where signage is to start [1] Staff Report.pdf, p. 6.
Sources
- Staff Report.pdf
- Agenda (PDF)
-
6 Park Signage (PR16) is listed under Parks and Recreation in the Town's 5-year CIP tables
Updated
The table text is jumbled, so we read the code as the General Plan element for this row [1] Table 1 - 5-Year CIP GP Consistency.pdf, p. 1.
Why it matters
The CIP tables place Park Signage (PR16) in the Parks and Recreation category [2] Agenda (PDF), p. 114.
Sources
- Table 1 - 5-Year CIP GP Consistency.pdf
- Agenda (PDF)