Initiative
Townwide striping / slurry seal
The Final Budget Adoption FY26-27 document says the Town started an annual slurry and fog seal program in 2024 and developed a plan to treat all roads in Town once every 5 years [1] Final Budget Adoption FY26-27.pdf, p. 44. The same document lists a FY26-27 total budget of $700,000 for the 2026 Slurry Seal Project and $200,000 for the 2026 Townwide Striping Project [2] Final Budget Adoption FY26-27.pdf, p. 36.1. A May 20, 2026 staff report says a contract for the 2026 Slurry Seal project had been awarded [3] May 2026 PW Engineering CIP Update.pdf, p. 1. Earlier bid records show the low base bid for the 2025 Slurry and Striping Project was $559,120.00 from VSS International, Inc. [4] Agenda (PDF), p. 14. The low base bid for the 2024 Slurry Seal project was $734,056.50 from Doolittle Construction LLC [5] Award contract for Slurry Seal 2024 project.pdf, p. 2.
Updated
Findings
12 findings
-
1 A contract for the 2026 Slurry Seal Project had been awarded by May 20, 2026
Updated
A May 6, 2026 staff report recommended that Town Council award the base bid for the 2026 Slurry Seal Project to the lowest responsive bidder, Pavement Coatings Co., for $399,663.90 [1] Award contract for 2026 Slurry Seal project.pdf, p. 1. The May 20, 2026 Public Works Engineering CIP Update says: "A contract has been awarded, and staff hope to complete the work by the end of June" [2] May 2026 PW Engineering CIP Update.pdf, p. 1. That update does not name the contractor [2] May 2026 PW Engineering CIP Update.pdf, p. 1.
The recommended scope was slurry seal plus linear striping and pavement markings on select roads [1] Award contract for 2026 Slurry Seal project.pdf, p. 1. The roads listed were Canyon Boulevard and Canyon Place, Lakeview Boulevard and Lakeview Road, Rainbow Lane and Rainbow Place, and Forest Trail (from Lakeview to Minaret) and Forest Lane [1] Award contract for 2026 Slurry Seal project.pdf, p. 1. The staff report says staff developed the possible scope in the fall of 2025 using road condition assessments and the funding available [1] Award contract for 2026 Slurry Seal project.pdf, p. 1.
The FY26-27 final document filed with the June 17, 2026 meeting says the Town has bid the slopes neighborhood for 2026 and that the Town road department crack sealed and patched the roads in the work area in advance [3] Final Budget Adoption FY26-27.pdf, p. 36.1. It says the work is expected over the summer and is funded by road rehabilitation dollars [3] Final Budget Adoption FY26-27.pdf, p. 36.1. In February 2026, the CIP update listed the 2026 Slurry Seal budget as TBD and said staff would prepare plans for work to be completed that summer [4] February 2026 Public Works Engineering CIP Update.pdf, p. 1.
Why it matters
The records show the 2026 slurry work moving from planning in February 2026, to a staff award recommendation on May 6, to an awarded contract reported on May 20, 2026 [4] February 2026 Public Works Engineering CIP Update.pdf, p. 1[1] Award contract for 2026 Slurry Seal project.pdf, p. 1[2] May 2026 PW Engineering CIP Update.pdf, p. 1.
Sources
- Award contract for 2026 Slurry Seal project.pdf
- May 2026 PW Engineering CIP Update.pdf
- Final Budget Adoption FY26-27.pdf
- February 2026 Public Works Engineering CIP Update.pdf
-
2 FY26-27 budget documents list $700,000 for the 2026 Slurry Seal Project and $200,000 for 2026 Townwide Striping
Updated
The Final Budget Adoption FY26-27 lists "Total Budget FY26-27: $700,000" for the 2026 Slurry Seal Project and "Total Budget FY26-27: $200,000" for the 2026 Townwide Striping Project [1] Final Budget Adoption FY26-27.pdf, p. 36.1[2] Final Budget Adoption FY26-27.pdf, p. 44[3] Final Budget Adoption FY26-27.pdf, p. 45.
That amount is shown in the "TOML - GF Committed" column [4] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1. Table 1, the CIP Budget Outlook for 25/26 Carry Over to 26/27, lists ST16, 2026 Slurry Seal Project, at $400,000, and ST17, 2026 Townwide Striping Project, at $215,000 [5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1. Both amounts are shown under "TOML - GF Committed" [5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1.
The May 20, 2026 CIP update lists a budget of $400K for 2026 Slurry Seal and $200K for Road Striping Maintenance [6] May 2026 PW Engineering CIP Update.pdf, p. 1. The cited pages do not explain how these different figures relate to one another [1] Final Budget Adoption FY26-27.pdf, p. 36.1[5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[6] May 2026 PW Engineering CIP Update.pdf, p. 1.
Why it matters
Different Town documents show different dollar figures for the 2026 slurry and striping work, each labeled differently [1] Final Budget Adoption FY26-27.pdf, p. 36.1[5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[4] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1[6] May 2026 PW Engineering CIP Update.pdf, p. 1. Readers should check which table a figure comes from [1] Final Budget Adoption FY26-27.pdf, p. 36.1[5] Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf, p. 1[4] Table 2 - CIP Budget Outlook for 26-27.pdf, p. 1[6] May 2026 PW Engineering CIP Update.pdf, p. 1.
Sources
- Final Budget Adoption FY26-27.pdf
- Final Budget Adoption FY26-27.pdf
- Final Budget Adoption FY26-27.pdf
- Table 2 - CIP Budget Outlook for 26-27.pdf
- Table 1 - CIP Budget Outlook for 25-26 Carry Over.pdf
- May 2026 PW Engineering CIP Update.pdf
-
3 The Town started an annual slurry and fog seal program in 2024 and plans to treat all roads once every 5 years
Updated
The Final Budget Adoption FY26-27 says that in 2024 the Town started an annual slurry and fog seal program, and that treatments were tested and evaluated in that initial year [1] Final Budget Adoption FY26-27.pdf, p. 44[2] Final Budget Adoption FY26-27.pdf, p. 36.1. It says that, based on the general success of the treatments, the Town developed a plan to treat all of the roads in Town once every 5 years [1] Final Budget Adoption FY26-27.pdf, p. 44[2] Final Budget Adoption FY26-27.pdf, p. 36.1.
It says that in 2025 the Town bid and awarded a slurry project to treat roads in the Knolls neighborhood, the first section of Town to be treated under the plan [1] Final Budget Adoption FY26-27.pdf, p. 44. For 2026, it says the Town has bid the slopes neighborhood [1] Final Budget Adoption FY26-27.pdf, p. 44.
Why it matters
The document filed with the June 17, 2026 meeting describes a neighborhood-by-neighborhood schedule, with the Knolls in 2025 and the slopes in 2026, under a stated 5-year cycle [1] Final Budget Adoption FY26-27.pdf, p. 44.
Sources
- Final Budget Adoption FY26-27.pdf
- Final Budget Adoption FY26-27.pdf
-
4 VSS International, Inc. submitted the lowest of six base bids, $559,120.00, for the 2025 Slurry and Striping Project
Updated
The agenda packet filed with the May 21, 2025 meeting says staff solicited bids beginning April 14, 2025, and opened them on May 9, 2025 [1] Agenda (PDF), p. 14. Six bids were received [1] Agenda (PDF), p. 14. The base bids were: VSS International, Inc. $559,120.00; Intermountain Slurry Seal, Inc. $567,874.95; Doolittle Construction $569,396.34; Sierra Nevada Construction, Inc. $707,714.40; Pavement Coatings Co. $710,264.58; and CR Contracting LLC $1,203,471.10 [1] Agenda (PDF), p. 14.
The May 21, 2025 staff report recommended awarding the base bid to VSS International, Inc. for $559,120.00 [2] Award contract for 2025 Slurry and Fog Seal project.pdf, p. 1. Its recommended scope was striping and painting, fog seal, and slurry seal on select roads [2] Award contract for 2025 Slurry and Fog Seal project.pdf, p. 1. The FY25-26 Final Budget lists "Total Budget FY25-26: $560,000" for the 2025 Slurry and Striping Project (ST2) [3] FY25-26 Final Budget.pdf, p. 34.1.
The October 2025 project closeout says the project was bid with several alternates, but only the base bid was awarded and completed [4] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2[5] Agenda (PDF), p. 44. It says the alternate road segments will remain in consideration for future treatments [4] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2.
Why it matters
The records show the 2025 project's bid range, the staff-recommended low bid, and a listed FY25-26 budget of $560,000 [1] Agenda (PDF), p. 14[2] Award contract for 2025 Slurry and Fog Seal project.pdf, p. 1[3] FY25-26 Final Budget.pdf, p. 34.1[4] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2. They also show that only the base bid was carried out [1] Agenda (PDF), p. 14[2] Award contract for 2025 Slurry and Fog Seal project.pdf, p. 1[3] FY25-26 Final Budget.pdf, p. 34.1[4] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2.
Sources
- Agenda (PDF)
- Award contract for 2025 Slurry and Fog Seal project.pdf
- FY25-26 Final Budget.pdf
- Project Closeout_2025 Slurry and Fog Seal.pdf
- Agenda (PDF)
-
5 In 2025, slurry seal went on Knolls-area roads, the SHARP parking lot and other streets, and fog seal on newer roads
Updated
The 2025 Year in Review, in the agenda packet for the April 1, 2026 meeting, lists streets that received slurry seal in 2025 [1] Agenda (PDF), p. 153. They include the SHARP parking lot, N Frontage Road, Sierra Boulevard, Old Mammoth Road and Sawmill Cutoff Road [1] Agenda (PDF), p. 153. It lists streets that received fog seal, including Commerce Circle, Laurel Mountain Road, Red Fir Road, Mono Street, Mountain Boulevard, Kelley Road and the College Connector Path [1] Agenda (PDF), p. 153. It says linear striping for fog lines, bike lanes and center lines was applied to all roads throughout Town, and pavement markings went on roads that received either seal [1] Agenda (PDF), p. 153.
The October 2025 project closeout says staff selected all roads in the Knolls neighborhood, plus all other roads north of Main Street between Minaret Rd/HWY 203 and Sawmill Cutoff, for slurry seal [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2. It says staff selected all roads constructed within the last five years, except Inyo St. and the Chaparral extension, for fog seal [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2.
Why it matters
These records list which streets received slurry or fog seal in 2025, the first neighborhood treated under the Town's 5-year plan [1] Agenda (PDF), p. 153[2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2[3] Final Budget Adoption FY26-27.pdf, p. 44.
Sources
- Agenda (PDF)
- Project Closeout_2025 Slurry and Fog Seal.pdf
- Final Budget Adoption FY26-27.pdf
-
6 The Town is moving annual linear striping from Public Works crews to an outside contractor
Updated
The FY26-27 final document filed with the June 17, 2026 meeting says all linear striping in Town has typically been re-painted by Public Works staff each year in the spring [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It says that by developing a plan set and contracting externally, the Town can have its striping completed annually once spring weather permits, while freeing Public Works staff for other maintenance [1] Final Budget Adoption FY26-27.pdf, p. 36.1. It lists the 2026 Townwide Striping Project at "Total Budget FY26-27: $200,000" and says the project is expected to be completed by late spring 2026 [1] Final Budget Adoption FY26-27.pdf, p. 36.1.
The October 2025 closeout for the 2025 slurry and fog seal project says the contract's striping and pavement markings reduced the Public Works Road Crew's summer work [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2. It also says a downside of combining striping with the seal project was that the roads were not painted until much later in the summer than desired [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2. It says staff recommends a separate maintenance contract for painting only, so the work is completed earlier in the spring [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2.
The February 18, 2026 CIP update says staff was preparing plans to bid an annual road striping maintenance contract, with work in early spring each year and the budget listed as TBD [3] February 2026 Public Works Engineering CIP Update.pdf, p. 1. A staff report in the document filed with the April 1, 2026 meeting says staff solicited bids at the beginning of March, with bids scheduled to be opened at 4:00 PM on March 27, 2026 [4] Award contract for Annual Road Striping Maintenance.pdf, p. 2. It says the striping project is estimated to cost approximately $300,000 annually, and that the Town budgets $580,000 annually for various road rehabilitation and maintenance purposes [4] Award contract for Annual Road Striping Maintenance.pdf, p. 2. Staff proposed funding the recommended bid plus 10% contingency from the Town's annual road rehab balance [4] Award contract for Annual Road Striping Maintenance.pdf, p. 2.
The May 20, 2026 CIP update lists Road Striping Maintenance at $200K. It says the contractor would start layout and removal of old conflicting striping on Monday, May 18, and plan to start painting on Tuesday, May 26 [5] May 2026 PW Engineering CIP Update.pdf, p. 1.
Why it matters
The records show a progression from the 2025 closeout's recommendation of a separate painting contract, through a February 2026 plan and an April 2026 bid process, to contractor work scheduled for May 2026 [2] Project Closeout_2025 Slurry and Fog Seal.pdf, p. 2[3] February 2026 Public Works Engineering CIP Update.pdf, p. 1[4] Award contract for Annual Road Striping Maintenance.pdf, p. 2[5] May 2026 PW Engineering CIP Update.pdf, p. 1.
Sources
- Final Budget Adoption FY26-27.pdf
- Project Closeout_2025 Slurry and Fog Seal.pdf
- February 2026 Public Works Engineering CIP Update.pdf
- Award contract for Annual Road Striping Maintenance.pdf
- May 2026 PW Engineering CIP Update.pdf
-
7 Doolittle Construction LLC submitted the lowest of seven base bids, $734,056.50, for the 2024 Slurry Seal project
Updated
Seven bids were received [1] Award contract for Slurry Seal 2024 project.pdf, p. 2. The next-lowest was American Asphalt South, Inc. at $744,710.95 [1] Award contract for Slurry Seal 2024 project.pdf, p. 2. The report says the low bid was below the engineer's estimate of $900,000 [1] Award contract for Slurry Seal 2024 project.pdf, p. 2.
The November 2024 project closeout says the contract was awarded at the May 15, 2024 Town Council meeting to Doolittle Construction, LLC for $734,056.50, including authorization of up to an additional 10% [2] Project Closeout_2024 Slurry Seal.pdf, p. 2. It says the total cost, including construction prep, change orders and incidentals, came in under the originally identified project budget of $807,462.15 [2] Project Closeout_2024 Slurry Seal.pdf, p. 2.
The 2024 Street Slurry Seal Project (ST16) shows "Total Budget FY24-25: $900,000" in the agenda packet filed with the June 19, 2024 meeting [3] Agenda (PDF), p. 291[4] Agenda (PDF), p. 204. It shows "Total Budget FY24-25: $715,000" in the packet filed with the December 4, 2024 meeting [3] Agenda (PDF), p. 291[4] Agenda (PDF), p. 204.
Why it matters
The 2024 project was awarded below the engineer's estimate and, per the closeout, finished under its originally identified budget [1] Award contract for Slurry Seal 2024 project.pdf, p. 2[2] Project Closeout_2024 Slurry Seal.pdf, p. 2.
Sources
- Award contract for Slurry Seal 2024 project.pdf
- Project Closeout_2024 Slurry Seal.pdf
- Agenda (PDF)
- Agenda (PDF)
-
8 Slurry seal was completed on seven named streets in summer 2024 under a contract awarded in May 2024
Updated
The 2024 Annual Planning Report (filed with the May 14, 2025 meeting) says a contract was awarded in May 2024 and slurry seal work was completed over the summer on seven streets [1] 2024 Annual Planning Report.pdf, p. 16[2] Agenda (PDF), p. 68. The streets were Minaret Road, Chateau Road, Old Mammoth Road (from Minaret Road to Club Drive), Meridian Boulevard, Azimuth Drive, Canyon Boulevard and Forest Trail [1] 2024 Annual Planning Report.pdf, p. 16. The report says the streets were selected after an analysis in the fall of 2023 [1] 2024 Annual Planning Report.pdf, p. 16. The report describes a Type II seal as using aggregate as large as 1/4 inch [1] 2024 Annual Planning Report.pdf, p. 16.
The report says contracted striping reduced the crew's workload that summer [1] 2024 Annual Planning Report.pdf, p. 16. The June 2024 budget page for the 2024 Street Slurry Seal Project (ST16) says the scope included striping and that portions of Old Mammoth and Lakeview were bid as alternatives [3] Agenda (PDF), p. 291.
Why it matters
The records name the streets treated in the first year of the annual program and show that contractor striping was already part of the 2024 project [1] 2024 Annual Planning Report.pdf, p. 16[3] Agenda (PDF), p. 291.
Sources
- 2024 Annual Planning Report.pdf
- Agenda (PDF)
- Agenda (PDF)
-
9 The 2024 slurry seal was funded from a $2,425,000 Fund 210 road-maintenance balance
Updated
The May 15, 2024 staff report says this covers annual crack sealing, pothole repair, striping and pavement markings, and other rehabilitation projects [1] Award contract for Slurry Seal 2024 project.pdf, p. 2. Staff recommended allocating the bid plus 10% contingency, for a total of $807,462.15 [1] Award contract for Slurry Seal 2024 project.pdf, p. 2.
In the same May 15, 2024 agenda packet, the Road and MUP Rehab 2024 Project had two bids [2] Agenda (PDF), p. 138. Qualcon Contractors, Inc. had the low base bid of $2,707,194.25, and Spiess Construction Co, Inc. bid $3,073,145.65 [2] Agenda (PDF), p. 138. The engineer's estimate was $3,200,000 [2] Agenda (PDF), p. 138. The report says staff recommended using funds from unallocated capital reserves to cover the base bid and Alternate 1 plus 10% contingency, for a total of $3,087,033.68 [2] Agenda (PDF), p. 138. The MCWD portion (Alternate 1) is valued at approximately $109,120 and is to be reimbursed to the Town by MCWD [2] Agenda (PDF), p. 138.
Why it matters
The staff reports show the 2024 slurry seal and a larger road rehabilitation contract drawing on the same Fund 210 balance, which the Town says also pays for annual striping and pavement markings [1] Award contract for Slurry Seal 2024 project.pdf, p. 2[2] Agenda (PDF), p. 138.
Sources
- Award contract for Slurry Seal 2024 project.pdf
- Agenda (PDF)
-
10 Bluffs assessment district reports list $3,000 for striping in FY2019/20 and FY2020/21 and $0.00 in FY2022/23 and FY2023/24
Updated
The Annual Report for Assessment District 93-4, Zone 1 (The Bluffs), filed with the May 15, 2019 meeting, lists a proposed FY2019/20 cost of $3,000.00 for striping [1] Annual Report, p. 6. The same report lists a Slurry Seal – Accrual of $7,000.00 [1] Annual Report, p. 6. The Annual Engineer's Report filed with the June 3, 2020 meeting lists a proposed FY2020/21 striping cost of $3,000.00 and a Slurry Seal – Accrual of $0.00 [2] Annual Engineer’s Report, p. 6.
The FY2022/23 Engineer's Report lists proposed striping of $0.00 and a CIP Accumulation of $244,595.00 [3] FY 2022-23 Engineer's Report_The Bluffs.pdf, p. 6. The FY2023/24 report lists proposed striping of $0.00 and a CIP Accumulation of $193,512.00 [4] FY 2023-24 Engineer's Report_Bluffs.pdf, p. 6. Both reports define CIP Accumulation as the cost of periodic asphalt fog seal, slurry seal and replacement, and say fog seals and slurry seals typically alternate and occur every three years [3] FY 2022-23 Engineer's Report_The Bluffs.pdf, p. 6[4] FY 2023-24 Engineer's Report_Bluffs.pdf, p. 6.
Why it matters
The later reports carry a larger CIP Accumulation line for seal treatments [1] Annual Report, p. 6[2] Annual Engineer’s Report, p. 6[3] FY 2022-23 Engineer's Report_The Bluffs.pdf, p. 6[4] FY 2023-24 Engineer's Report_Bluffs.pdf, p. 6.
Sources
- Annual Report
- Annual Engineer’s Report
- FY 2022-23 Engineer's Report_The Bluffs.pdf
- FY 2023-24 Engineer's Report_Bluffs.pdf
-
11 Black Gold and Town staff slurry sealed the Community Center parking lots in fall 2022
Updated
A document in the agenda packet for the October 4, 2022 meeting says: "this fall Black Gold and Town Staff performed patch repair, crack sealing, and installed a slurry seal over the upper and lower Community Center Parking lots" [1] Agenda (PDF), p. 126. A document in the agenda packet for the September 6, 2022 meeting had said Black Gold and Town Staff would be doing this work, and that Town staff would install the vehicle and ADA striping [2] Agenda (PDF), p. 14.
Why it matters
The records show a slurry seal on a Town facility lot in 2022, with the striping planned for Town staff [1] Agenda (PDF), p. 126[2] Agenda (PDF), p. 14.
Sources
- Agenda (PDF)
- Agenda (PDF)
-
12 A 2016 parks maintenance list estimated $25,000 to stripe and slurry seal the Multi-Use Facility parking lot
Updated
A Town parks major maintenance and capital improvements list updated 11-29-16 (filed with the December 6, 2016 meeting) has a Multi-Use Facility item, "STRIPE AND SLURRY SEAL PARKING LOT", with $25,000 [1] J & K.docx, p. 1. The list is headed as preliminary conceptual cost estimates [1] J & K.docx, p. 1.
Why it matters
The record shows the Town carried a preliminary $25,000 estimate in 2016 for striping and slurry sealing this parking lot [1] J & K.docx, p. 1.
Sources
- J & K.docx